ST1002-CN120227 (2) CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Old Town Coppell and Bethel Road Infrastructure
Improvements (ST 10 -02)
CONTRACTOR: JRJ Paving, L.P.
OWNER: City of Coppell
CHANGE ORDER NO.: Three (3) DATE: February 27, 2012
1. This change order provides for compensation for finish grading the 32 patio home lots on
Lot 1, Block F, and the 12 patio homes on lot 2, Block G.
2. This change order is based on the plans dated February 1, 2012 by Glenn Engineering.
3. This change shall be total compensation for furnishing all materials, tools, equipment, labor,
survey staking, and other incidentals necessary to complete the work.
Item Description Quantity Unit Unit Price Total
ADD: 1 Grade lots per plan 1 LS $42,095.90 $42,095.90
Total Revision to Contract Amount $42,095.90
Original contract amount $4,350,190.39
Net increase in contract amount $42,095.90
Previously approved changes $74,677.00
Revised contract amount $ 4,466,963.29
Cumulative increase in TOTAL change order amount (Percentage) 2.7%
Net increase in contract time of completion 0
Revised Contract time of completion 350 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.