ST8503-CS 861015 Lone Star Gas Company
October 15, 1986
Ginn, Inc.
Mr. Gabe Favre
16135 Preston Road
Suite 106
Dallas, Texas 75248
Dear Mr. Favre:
On October 14, 1986, we met to discuss the City of Coppell's
street improvement and drainage plans for Bethel School Road.
During the week of October 6-10, we dug up our 8" gas main in
several locations along Bethel School Road and took grade shots
at each location. We then plotted this information on the plans
that your firm furnished us. The information obtained indicates
that our 8" main located along the north right-of-way line is in
conflict with the proposed grade and the proposed drainage line.
As we discussed in our meeting, to relocate the approximately
3500' of 8" gas main there are several factors to consider.
The estimated cost of this project is $60,000.00 and it will
take about fifty (50) days to prepare the paperwork, get approval,
and secure bids. This number of days will put us into the winter
months, and since this 8" line is our major feed line that supplies
the City of Coppell, it will be almost impossible to take it out
of service to make the necessary tie-ins. Not only will we be
concerned with foul weather, but also temperatures below 40 degrees.
The type and severity of weather we get will certainly affect our
time frame in completing this project. I would estimate forty-five
(45) working days to complete our work.
Sincerely,
VJerry A. Sauer
C&R Supervisor
Coppell
JAS/slb