ST8201-CS 890602GINN, INC.
CONSULTING ENGINEERS
June 2, 1989
Mr. Scott Balch, P.E.
L.H. Lacy Co.
P.O. Box 541297
Dallas, TX 75354-1297
Re:
Denton Tap Road Improvements from Belt Line Road to
Sandy Lake Road - Underground Lawn Irrigation System
Repairs and Adjustments
Dear Mr. Balch:
As discussed in our weekly progress meetings of May 23 and May
30, 1989, we have received and are in the process of reviewing
your May 5, 1989 letter requesting a Field Change to cover extra
work associated with repair and adjustment of irrigation systems
adjacent to the new pavement. It is our intention to cover this
item upon completion under Field Change No. 16. As previously
explained, we view simple removal of sprinkler heads and capping
of irrigation lines as adjustment of adjacent utilities and
therefore not eligible for payment as extra work. Replacement of
irrigation systems and components beyond the existing Right-of-
Way will be reimbursed under Field Change No. 16 provided the
work is authorized in advance by our Resident Project
Representative, Mr. Fleming.
If you have any questions, please call me.
Sincerely,
Project Engineer
cc:
Russell Doyle, P.E.
H. Wayne Ginn, P.E.
Randy Fleming
File 378 & 379
17103 Prcston Road · Suitc 100 · LB 118 ·Dallas, Tcxas 75248 · Phonc 214/248-4900