ST8201-CS 890511GINN, INC.
May 11, 1989
Mr. Russell Doyle, P.E.
City of Coppell
P.O. Box 478
Coppell, TX 75019
CONSULTING ENGINEERS
Re:
Denton Tap Road Improvements from
Belt Line Road to Sandy Lake Road - McDonalds
Dear Mr. Doyle:
This letter is in response to your Handwritten Memorandum dated
4/24/89 with a handwritten note dated 5/7/89. The weather we
have experienced since May 2, 1989 has caused a delay of about 4
working days (6 calendar days) in completion of the section of
pavement in front of McDonalds. According to the Contractor's
stated intentions in the Monday, May 8, 1989 progress meeting, he
intends to pour the two outside lanes this Thursday and the
inside lane and two driveways this Friday. This will roughly
translate to possibly opening driveways and the new paving by
Tuesday afternoon, May 16, 1989, if the concrete test cylinders
break above 3000 psi. This schedule "guestimate" does not
include any lost time due to further weather problems.
Please call me if you have any questions.
Sincerely,
John C. Karlsruher, P.E.
Project Engineer
JCK/dsp
cc:
Scott Balch, P.E.
H. Wayne Ginn, P.E.
Randy Fleming
File 378/260
17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas 75248 · Phone 214/248-4900