ST8201-CS 890503 GINN, INC.
May 3, 1989
CONSULTING
ENGINEERS
Mr. Scott Balch, P.E.
L. H. Lacy Company
P.O. Box 541297
Dallas, Texas 75354-1297
Re:
Denton Tap Road Improvements from Belt Line Road To Sandy
Lake Road - Change Order No. 2.
Dear Mr. Balch:
We are transmitting herewith two (2) fully executed copies of
Change Order No. 2 to the subject project. This Change Order No.
2 restores the original Contract Unit Prices for Lime Treatment
of the subgrade soils for the subgrade which was not treated with
Cement under Change Order No. 1. It also adds 14 calendar days
to the Contract Time making your new Contract completion date
June 28, 1989.
Please call if you have any questions.
Sincerely,
Karlsruher, P.E.
Project Engineer
enclosures
cc: ~~!??
H. Wayne Ginn, P.'E.
Randy Fleming
File J - 378/Contractor (a:co2378tr)