ST8201-CS 820520MEMO TO:
FROM:
SUBJECT:
Wayne Ginn, P.E.
Kevin Peiffer
Belt Line/Denton Tap Road Intersection
Sumnary - Cost Estimates for Improvements
Our file contains only one firm's cost estimates for improvements to^Belt
Line/Denton Tap Road intersection. These cost estimates were prepared by
Urban Systems Consultants, Inc. and consisted of four (4) alternatives.
These alternatives ranged from $630,000 to $1,000,000. The recommendations
made as a result of these estimates kept the number of alternatives to
two (2), a $630,000 and a $830,000 estimate, with the latter being the one
most highly reconanended.
The breakdown for the $830,000 estimate was as follows:
R.O.W. Cost
Construction Cost
Signal Construction Cost
Engineering Design Cost
$255,000
480,000
65,000
30,000
TOTAL = $830,000
None of their cost estimates specified which type of road material was
considered in preparing the estimates.
Kevin Peiffer
cc: File