LAW OFFICES OF
JACK GAY
ATTORNEY AT LAW
June 28, 1988
Att: STEVE GORAM
Gentlemen:
Re: John Adams
Drainage Easement
Coppell, Texas
Your presents at the meeting of May 24, 1988 was appreciated
and we trust that you have had time to review the drainage matter
since that date.
At the meeting you seemed to take a position that the city
has no liability to Mr. Adams. It is my theory that the city has
an obligation to all landowners regarding drainage. The
Indemnity agreement represents only a part of your
responsibility.
In your case the city would seem to have a dual
responsibility in that the city has been appointed to provide
comprehensive management of the floodplains in the city.
At the meeting, all parties were given until September 15,
1988 in order to take some positive action toward a satisfactory
resolution of the matter. In the event the matter is not
resolved to the satisfaction of Mr. Adams by that date, a suit
will be filed on the 16th with the city as a party.
if you desire to avoid the.litigation, you should kava ample
time to take action by the 15th of September. If you have any
suggestions or desire to discuss the matter in more detail,
please give me a call.
Verily yours,
Copies to:
LAWRENCE JACKSON
ATTORNEY, CITY OF COPPELL
1800 LINCOLN PLAZA
DALLAS, TEXAS 75201
23 MAY 1988
ESTIMATED coST FOR THE CONSTRUCTION OF 96-INCH REINFORCED CONCRETE PIPE
FROM 159 FEET NORTH OF COPPELL ROAD AT STATE HIGIIWAY 121 TO DENTON CREEK.
Ail work itcms are as estimated without the aid of soil boring, therefore
some items may not be shown and others may not be required.
ITEM
QUANT].TY UNIT PRICE COST
]. Remove conc headwall and apron
2. Remove 48-inch RC Pipe Culvert
3. Remove and replace fence
4. Remove and salvage 96-inch RC Pipe
5. For 96-inch R.C. Pipe complete in place
6. Reinforced concrete for pipe headwall
7. Rock for pipe embedment
8. Compacted backfill (using surplus exc.)
1 ea LS 1,200
24 LF LS 500
155 LF 6.55 1,015
42 LF LS 1,500
544 LF 275.00 149,600
12.5 CY 369.00 4,612
553 CY 30.00 16,590
145 CY 3.00 435
10% Contingency
$175,452
17,545
Estimated Engineering Fee for the approved design
of the Project: 10%.x Est. Constr. Cost ($192,997)=
$192,997
19,300
TOTAL ESTIMATED COST: $212,297