Asbury Manor-CS 971006 Coppell, Texas 75019
~~ The City With A Beautiful Future 214-462-0022
October 6, 1997
Fred Phillips
Ryland Homes
12000 Ford Road, Suite 320
Dallas, TX 75234
RE: Asbury Manor
Development Fee Assessment
Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with a copy
of the Development Fee calculations for the referenced development.
Please make payment to the City of Coppell in the amount of $142,090.00 and forward to the
Finance Department along with a copy of the Fee Assessment table. This amount is a portion
of the assessed fees which need to be paid prior to Council approval. Please refer to attached
table for additional fees. Also provide a copy of the Engineer's estimate or contract to our office
so the construction inspection fee can be verified.
Providing a copy of your paid receipt to the Engineering Department will help us to verify the
payment of required fees and insure a successful beginning of this project. We look forward
to working with you on this project. If you have any questions, please contact me.
Sincerely, Q
KEnneth M. Grif m, P.E.
Assistant City Manager/City Engineer
cc: Jennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Matt Cast, Supt. of Public Services
Greg Jones, Chief Building Official
Gary Sims, Dir. Leisttre Services
DEVELOPMENT FEE TABLE
Project: Asbury Manor
Date: 10/6/97
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $22,950.00 $22,950.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $2,350.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $1,110.44
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $144.38
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $1,380.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $35.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $20,700.00 $20,700.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $2,300.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $2,300.00
(100% due at Issuance of Building Permi0
Park Fee $59,110.00 $59,110.00
(100% due prior to Council Approval)
Roadway Impact Fee $39,330.00 $39,330.00
(100% due prior to Council Approval)
Street Light Fee Information not
(100% due prior to Acceptance of Project available at this time
Street Sign Fee Information not
(100% due prior to Acceptance of Project available at this time
Construction Inspection Fee Need submittal of
development contracts
TOTAL $151,709.82
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $142,090.00
b~VELOPMENT FEE WORKSHEET
PROJECT: Asbury Manor
DATE: 10/6/97
Water Impact Fee:
Domestic Meter(s): 46 - 5/8 inch X 3/4 inch 46 ESU's
Irrigation Meter(s): I - I 1/2 inch 5 ESU's
ESU's
Fireline Meter(s): ESU's
Total #: 51 ESU's @ $450.00 ea. $22,950.00
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total #: 47 Connections @ $50.00 ea. $2,350.00
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Water Meter Fee (Domestic):
Total #: 46 Domestic Meter(s) @ $24.14 $1,110.44
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Water Meter Fee (Irrigation/Fireline):
Total #: I Irrigation Meter(s) @ $144.38 $144.38
Total #: 0 Additional Irrigation Meter(s) @ $0.00
Total #: 0 Fireline Meter(s) @ $0.00
(100% due prior to issuance of water meters)
Water Meter Deposit Fee (Domestic):
Total #: 46 Meter(s) @ $30.00 ea. $1,380.00
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: I Meter(s) @ $35.00 ea. $35.00
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU' 46 @ $450.00 ea. $20,700.00
Wastewater Tap Inspection Fee:
Total #: 46 Connections @ $50.00 ea. $2,300.00
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 46 Lots @ $50.00 ea. $2,300.00
(100% due prior to issuance of building permit)
Page I
,. EVELOPMENT FEE WORKSH=ET
Park Fee (For Resdential Developments Only):
* Preliminary plat approved prior to June 23, 1992:
N/A Single-family @ $150.00 / Lot N/A
N/A Multi-family @ $75.00 / Unit N/A
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after June 23, 1992:
N/A Single-family @ $350.00 / Lot N/A
N/A Multi-family @ $350.00 / Unit N/A
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after October 26, 1993:
46 Single-family @ $1285.00 / Lot $59,110.00
N/A Multi-family @ $1285.00 / Unit N/A
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations) $39,330.00
Street Lighting Fees: Information not
Assessed for lighting in the City's right-of-way, available at this time
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees: Information not
Assessed for signage in the City's right-of-way, available at this time
(See attached fee calculations if applicable)
Construction Inspection Fees: Need submittal of
A copy of the development contract must be submitted for assessment, development contracts
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Page 2
ROA~ WAY IMPACT FEE CALCUL~ £IONS
PROJECT: Asbury Manor
DATE: 10/6/97
ROADWAY IMPACT FEE:
Service Area * 1
Category ** Residential
Land Use ** Single-Family Detached
Building Size (Sq. Ft.) N/A
Development Units ** 46
Vehicle Miles per Development Unit ** 2.85
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Development Units) x
Vehicle Miles per Development Unit) x (Fee Per Vehicle Mile) = $39,330.00
· (Figure 2 - Roadway Impact Fee Study)
· * (Table 3 - Roadway Impact Fee Study)
· ** (Schedule 2, Page 3 - Roadway Impact Fee Study)