WA9601-CS 980420 SHIMEK, JACOBS & FINKLEA, L.L.P.
CONSULTING ENGINEERS
8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361~0204 Phone (214) 361-7900
RONALD V. CONWAY, P.E.
JOHN W. BIRKHOFF, P.E.
JOE R. CARTER, P.E. April 20, 1998
GARY C. HENDR1CKS, P.E.
I. C. FINKLEA, P.E.
~d 76177 "': ) '
Re: City of Coppell
Wagon Wheel Ranch Elevated Storage Tank
Change Order No. 1
Gentlemen:
We are enclosing two copies of Change Order No. 1 to your contract with the City of Coppeil, dated March
10, 1998, for the construction of the Wagon Wheel Ranch Elevated Storage Tank. Change Order No. 1
covers the construction of a segment of the 24-inch Sandy Lake Road Water Line requested by the City.
Please submit your proposal and cost estimates for the items listed. If you have any questions, please direct
them to us.
J XCoppellN94156~X~nstXCO4_Llr doc
CITY OF COPPELL, TEXAS
WAGON WHEEL RANCH ELEVATED STORAGE TANK
Project No. WA-96-01
Bid No. Q0198-03
CHANGE ORDER NO. 1
A. INTENT OF CHANGE ORDER
The intent of this change order is to modify the provisions of the contract entered into between the City of
Coppell, Texas and Landmark Structures, Inc., 1665 Harmon Road, Fort Worth, Texas 76177, for
construction of the Wagon Wheel Ranch Elevated Storage Tank, dated March 10, 1998.
B. DESCRIPTION OF CHANGE
As directed by the City of Coppell, 1940 linear feet of 24-inch waterline is to be constructed along Sandy
Lake Road from Coppell Road to Whispering Hills Drive. This work is added in an effort to coordinate
with construction for a new development in the vicinity.
C. EFFECT OF CHANGE ON CONTRACT AMOUNT
This change order will have the following effect on the cost of this project:
No. Description Quantity This C.O. Quantity Unit Price of Change
//2 Furnish and Install 24" Water Line by 0 1,589 1,589 L.F.
including Embedmeat
,fi Furnish and Install 24" Water Line by 0 215 215 L.F.
other than Open Cut
4 Furnish and Install 24" Water Line with 0 136 136 L.F.
36" Encasemeat Pipe, by other than
Open Cut
5 Furnish and Install 8" PVC Water Line, 0 65 65 L.F.
with Embedmeat
6 Furnish and Install 24" Butterfly Valve 0 2 2 Ea.
7 Fumish and Install 12" Gate Valve 0 2 2 Ea.
8 Fumish and Install 8" Gate Valve 0 5 5 Ea.
9 Furnish and Install 6" Air and Vacuum 0 1 1 Ea.
Release Valve
10 Furnish and Install 24" Flanged Dished- 0 2 2 Ea.
Head Plug
11 Connect to Existing 8" Waterline 0 1 1 Ea.
12 Cut & Plug Existing 8" Waterline 0 2 2 Ea.
13 Remove & Replace Existing Asphalt 0 61 61 S.Y.
Pavement
j:\clerieaI\coppell\96-149Xspecs\co-ldoc (4/20/98) Page 1 of 2
No. Description Quantity This C.O. Quantity Unit Price of Change
14 Extra Crushed Stone for Embedment 0 15 15 C.Y.
15 Furnish, Install, Maintain &Removal of 0 1 I L.S.
Erosion Control Devices
16 Furnish, Install & Maintain Traffic 0 1 1 L.S.
Control Devices
17 Design & Install Trench Safety Systems 0 1,940 1,940 L.F.
Original Contract Amount 2,256,717.00
Change Order No. 1
Revised Contract Amount
D. EFFECT OF CHANGE ON CONTRACT TIME
The work required under this change order will add calendar days to this project.
Original Contract Time 460 calendar days
Change Order No. 1 calendar days
Revised Contract Time calendar days
E. AGREEMENT
By the signatures below, duly authorized agents of the City of Coppell, Texas and Landmark Structures,
Inc., do hereby agree to append this Change Order No. 1 to the original contract between themselves, dated
March 10, 1998.
City of Coppell, Texas Landmark Structures, Inc.
Owner Contractor
By: By:
Date: Date:
Attest: Attest:
j:\clerical\coppell\96-149XspecsXco-l.doe (4/20/98) Page 2 of 2