Ok. As long as we're on the same page.
Keith
-----Original Message-----
From: "Marty Murphy" <Martym@JRJPaving.com>
To: Keith Marvin <KMARVIN@coppelltx.gov>
Cc: Leslie Henderson <LHENDERSON@coppelltx.gov>
Cc: Rhonda Adloo <RADLOO@coppelltx.gov>
Cc: Richard Odell <RODELL@coppelltx.gov>
To: <Tedl@JRJPaving.com>
Sent: 10/26/2011 9:53:37 AM
Subject: RE: Old Town/Bethel
You are correct regarding our last meeting. I hoped to have all of this
to you by last Friday and that obviously did not happen. I have had Tad
verifying the widths we have for the detour widening at Bethel and
Coppell and discussing timelines with my utility sub. I am still working
on this and do understand that this work cannot happen for two weeks
after this plan is approved.
Marty Murphy,
Business Manager
JRJ Paving, LP
1805 Royal Lane, Ste. 107
Dallas, TX. 75229
214-466-8340
214-466-8354 Fax
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, October 26, 2011 9:19 AM
To: Marty Murphy; Tedl@JRJPaving.com
Cc: Leslie Henderson; Rhonda Adloo; Richard Odell
Subject: RE: Old Town/Bethel
Marty,
(4/18/2012) Keith Marvin - Re: Old Town/BethelPage 2
When we met last week we talked about schedules and sequences of work on
Bethel Road. When we left the meeting I understood you would be
verifying your approach and sending a preliminary plan and schedule for
our review and comment. I believe we were clear on the fact we need two
weeks notice prior to any road closure.
At this time I have still not received your proposed schedule or
preliminary traffic plan. Please forward them at your earliest
opportunity so we can begin to make the proper notifications.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 10/14/2011 2:26 PM >>>
Got it, sending it out for an answer on the file type. I did get your
answer on JBC and you are correct they have confirmed that. We are
contacting all of the other bidders on the list.
Marty Murphy,
Business Manager
JRJ Paving, LP
1805 Royal Lane, Ste. 107
Dallas, TX. 75229
214-466-8340
214-466-8354 Fax
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Friday, October 14, 2011 10:11 AM
To: Marty Murphy
Cc: Leslie Henderson; Rhonda Adloo; Richard Odell
Subject: Old Town/Bethel
Marty,
Attached are the pages from the addendum that were not included in your
executed contract. Please add these to your copy. I have the artwork
for the sign face in electronic format, and will make it available in
the preferred file type of your sign manufacturer. Please let me know
what they need.
I also left you a message yesterday about John Burns Construction.
(4/18/2012) Keith Marvin - Re: Old Town/BethelPage 3
They do not appear on our list of approved Atmos installers. The three
vendors on our approved list were the only ones that appeared to be
acceptable to all franchise utility companies. If you have
documentation from the franchise utilities that John Burns is acceptable
to perform the joint trench work, please provide it for our
consideration.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681