(4/20/2012) Keith Marvin - Re: COR 1R 16 INCH WATER LINE CONFLICT 11-29-11Page 1
From:
Keith Marvin
To:
Martym@JRJPaving.com
Date:
11/30/2011 6:26 PM
Subject:
Re: COR 1R 16 INCH WATER LINE CONFLICT 11-29-11
I'll get you an answer tomorrow. It needs to go to council for approval, but more likely than not they will
approve our recommendation.
-----Original Message-----
From: "Marty Murphy" <Martym@JRJPaving.com>
To: Keith Marvin <KMARVIN@coppelltx.gov>
Sent: 11/30/2011 6:08:59 PM
Subject: Re: COR 1R 16 INCH WATER LINE CONFLICT 11-29-11
Understood since we know we have lead times on some of these parts it would great if we could know a
date when this will be released and we can preorder these parts so we are not delayed any further
Sent from my iPhone
Marty Murphy,
Business Manager
On Nov 30, 2011, at 5:24 PM, "Keith Marvin" <KMARVIN@coppelltx.gov> wrote:
> I think we're just going to raise up over the top. I'll look at it
> closer in the morning and let you know for sure.
>
> The boss wouldn't let me put the work that has already been done for
> investigation off onto a future change order. It looks like we will
> need to go to City Council for either option.
>
> Keith
> -----Original Message-----
> From: "Marty Murphy" <Martym@JRJPaving.com>
> To: Keith Marvin <KMARVIN@coppelltx.gov>
>
> Sent: 11/30/2011 5:16:01 PM
> Subject: RE: COR 1R 16 INCH WATER LINE CONFLICT 11-29-11
>
> So are you going to go with the re-route?
>
>
>
> Marty Murphy,
>
> Business Manager
>
>
>
> JRJ Paving, LP
>
> 1805 Royal Lane, Ste. 107
>
> Dallas, TX. 75229
>
(4/20/2012) Keith Marvin - Re: COR 1R 16 INCH WATER LINE CONFLICT 11-29-11Page 2
> 214-466-8340
>
> 214-466-8354 Fax
>
>
>
> From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
> Sent: Wednesday, November 30, 2011 5:15 PM
> To: Marty Murphy
> Subject: Re: COR 1R 16 INCH WATER LINE CONFLICT 11-29-11
>
>
>
> Marty,
>
>
>
> It looks like I'm going to have to go to City Council on December 13th
> with this change order. I'll add these additional items as well as an
> amount to be used at the city's discretion for investigation of
> additional lines as we proceed west.
>
>
>
> I'll get it written up and get it over to you to review.
>
>
>
> Keith
>
>
>
>
>
>
>
>
>
> Keith Marvin, P.E.
> Project Engineer
> (972) 304-3681
>
>>>> "Marty Murphy" <Martym@JRJPaving.com> 11/29/2011 4:26 PM >>>
>
> If you choose to raise the line, which we now have under $25k, can the
> investigation time and removal of the concrete blocking be put into a
> change order at another time?
>
>