Keith Marvin - FW: CPL09446 parking lot mods
From: Dan Prendergast <drp@freese.com>
To: Keith Marvin <kmarvin@coppelltx.gov>
Date: 11/30/2011 2:47 PM
Subject: FW: CPL09446 parking lot mods
CC: Tricia Hatley <thh@freese.com>
Keith,
Please see below for David’s thoughts on the electrical plan. I believe the part that we need clarification on the
most is #3. I’ll call you in a little while to discuss.
Thanks
Dan Prendergast, E.I.T.
East Transportation/Infrastructure
Freese and Nichols, Inc.
1701 N. Market St., Suite 500
Dallas, Texas 75202
214-217-2216
www.freese.com
From: David Beckman
Sent: Wednesday, November 30, 2011 2:31 PM
To: Dan Prendergast
Cc: Wade Zemlock; Tricia Hatley
Subject: CPL09446 parking lot mods
Dan,
Here’s my thoughts on how we handle the electrical modifications for this change:
1)Add receptacles to tree wells on Houston Street. These would be served from panel “LB” (city’s meter).
2)Add poles/fixtures for the new parking – 10 total, 1 in each island for the inboard parking and similar
locations for perimeter parking. It will not be necessary to add lighting for parking that is near Houston
Street.
3)New poles/fixtures to be served by new meter, panelboard, lighting contactor etc. Meter location to be
determined. We design 2 separate lighting circuits with separate conduit back to the panelboard. A
pullbox in each lighting circuit will serve as a future connection point.
a.The developer will pay for new meter, parking lot lighting etc. and be responsible for the
monthly electric bill.
b.When restaurant “A” builds, they can migrate their parking lot lighting circuit so it comes off the
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ED641F5City_...4/20/2012
Page 2 of 2
new meter serving the restaurant. The developer will continue to be responsible for paying the bill
for the remaining parking lot lighting (5 poles/fixtures).
c.When restaurant “B” builds they will migrate the remaining lighting circuit to their meter. The
existing electrical service, meter, and panelboard etc that served the 2 lighting circuits can now
be removed.
I need to know if this plan is satisfactory before I discuss new service arrangement with Oncor. In the meantime,
I’m going to proceed as if this is arrangement is OK.
Please advise if this is acceptable.
David Beckman
LEEDAP, LC
Freese and Nichols, Inc.
4055 International Plaza, Suite 200
Fort Worth, Texas 76109-4895
817 735 7341
817 735 7491 (Fax)
817 683 1568 (mbl)
dsb@freese.com
Please consider the environment before printing this message.
This electronic mail message is intended exclusively for the individual or entity to which it is addressed. This message, together with any attachment,
may contain the sender's organization's confidential and privileged information. The recipient is hereby notified to treat the information as confidential
and privileged and to not disclose or use the information except as authorized by sender's organization. Any unauthorized review, printing, retention,
copying, disclosure, distribution, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information by persons or
entities other than the intended recipient is prohibited. If you received this message in error, please immediately contact the sender by reply email and
delete all copies of the material from any computer. Thank you for your cooperation.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4ED641F5City_...4/20/2012