Keith Marvin - BETHEL RD STATUS
From: "Cheney, David" <david.cheney@twcable.com>
To: Keith Marvin <kmarvin@coppelltx.gov>
Date: 1/17/2012 8:50 AM
Subject: BETHEL RD STATUS
Hey Keith,
I wanted to let you know our fiber splicer’s were out all night last night/this morning splicing over to the new
fibers but could not finish all of due to them only having a 5 hr window. I will hopefully let you know by the end
of the day when we can schedule and complete that last of the fiber splicing. I apologize this didn’t get 100%
complete. I will keep you updated.
Thank you Keith
David Cheney
Construction Supervisor
Time Warner Cable
1565 Chenault St. Dallas, TX 75228
Office: 214-320-7406
This E-mail and any of its attachments may contain Time Warner Cable proprietary information, which is privileged, confidential, or subject to copyright
belonging to Time Warner Cable. This E-mail is intended solely for the use of the individual or entity to which it is addressed. If you are not the
intended recipient of this E-mail, you are hereby notified that any dissemination, distribution, copying, or action taken in relation to the contents of and
attachments to this E-mail is strictly prohibited and may be unlawful. If you have received this E-mail in error, please notify the sender immediately and
permanently delete the original and any copy of this E-mail and any printout.
file://C:\Documents and Settings\radloo\Local Settings\Temp\XPgrpwise\4F153655City_o...4/23/2012