Cameron Country-CS 980910The City With A Beautiful Future
P.O. BOX 478
COPPELL, TEXAS 75019
P.O. Box 478
Coppell, Texas 75019
972-462-0022
FILE
Jack Bommarito
Beamer Development, Inc.
P.O. Box 2312
Coppell, TX 75019
Cameron Country (812 Deforest)
Development Fee Assessment
September 15, 1998
Dear Mr. Bommarito:
Enclosed is a copy of thc City of Coppell Development Fee Assessment table, along with a copy
of the Development Fee calculations for the referenced development.
Please make payment to thc City of Coppell in the amount of $3,040.00 and forward to the
Finance Department along with a copy of the Fee Assessment table. This amount is a portion
of the assessed fees which need to be paid prior to Council approval. Please refer'to attached' ':
table for additional fees. Also provide a copy of the Engineer's estimate or contract to our office
so the construction inspection fee can be verified.
Providing a copy of your paid receipt to the Engineering Department will help us to verify the
payment of required fees and insure a successful beginning of this project. We look forward
to working with you on this project. If you have any questions, please contact me.
$i~.cerely,
Assistant City Engineer
CC:
Jennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Glenn Hollowell, Assistant Director of Public Works
Greg Jones, Chief Building Official
Gary Sims, Director of Leisure Services
DEVELOPMENT FEE TABLE
Project: Cameron Country (812 Deforest)
Date: 9/15/98
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $450.00 $450.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $50.00
(100% due at Issuance of Water Meter) '
Water Meter Fee (Domestic) $24.83
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $0.00
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $35.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $0.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $450.00 $450.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $50.00
(100% due at Issuance of Building Permit)
Park Fee $1,285.00 $1,285.00
(100% due prior to Council Approval)
Roadway Impact Fee $855.00 $855.00
(100% due prior to Council Approval)
Street Light Fee
(100% due prior to Acceptance of Project N/A
Street Sign Fee
(100% due prior to Acceptance of Project N/A
Construction Inspection Fee
N/A
TOTAL $3,249.83
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $3,040.00
DEVELOPMENT FEE WORKSHEET
PROJECT: Cameron Country (812 Deforest)
DATE: 9/15/98
Water Impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
1 - 5/8 inch X 3/4 inch = I ESU°s
= ESU's
= ESU's
= ESU's
Total #: 1 ESU's @ $450.00 ea.
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total #: 1 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total 0: 1 Domestic Meter(s) @ $24.83
(Single family due prior to issuance of building permit)
(Ail other developments due prior to issuance of meter)
lrrigation/Fireline Water Meter Fee:
Total #: 0 Irrigation Meter(s) @
Total #: 0 Additional Irrigation Meter(s) @
Total #: 0 Fireline Meter(s) @
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: I Meter(s) @ $35.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 0 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's:
@ $450.00 ea.
Wastewater Tap Inspection Fee:
Total 0: 1 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total 0: 1 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
$450.00
$50.00
$24.83
$0.00
$0.00
$o.oo
$35.00
$0.00
$450.00
$50.00
$50.00
Page I
DEVELOPMENT FEE WORKSHEET
Park Fee (For Residential Developments Only):
* Preliminary plat approved prior to June 23, 1992:
Single-family @ $150.00 / Lot
Multi-family @ $75.00 / Unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after June 23, 1992:
N/A
N/A
Single-family @ $350.00 / Lot
Multi-family @ $350.00 / Unit
(50% paid pdor to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after October 26, 1993:
1
N/A
Single-family @ $1285.00 / Lot
Multi-family @ $1285.00/Unit
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations)
SWeet Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
N/A
N/A
N/A
$1,285.00
N/A
$855.00
N/A
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
N/A
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
N/A
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
Cameron Country (812 Deforest)
9/15/98
ROADWAY IMPACT FEE:
Service Area *
Category ** Residential
Land Use ** Single-Family Detached
Building Size (Sq. Ft.) N/A
Development Units ** 1
Vehicle Miles per Development Unit ** 2.85
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Development Units) x
Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) --
$855.00
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)