Loading...
ST1002-CN120430 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Old Town Coppell and Bethel Road Infrastructure Improvements (ST 10-02) CONTRACTOR: JRJ Paving, L.P. OWNER: City of Coppell CHANGE ORDER NO.: Four (4) DATE: April 30, 2012 1. This change order modifies the joint trench installation of the conduit for Franchise Utilities. New pay items are added for secondary hand holes and pipe stub-ups. 2. This change order modifies the parking lane striping from 3-M Staymark to thermoplastic. 3. This change adds a pay item for a segmental block retaining wall to be built in front of the old Minyard Store adjacent to the project. This wall is necessary as a result of the grade changes associated with this project. 4. Finally this change revises the electrical plans by replacing the rack mounted power service with a black powder coated pedestal, and includes a timer and photocell for the tree well receptacles. Item Description Quantity Unit Unit Price Total ADD: 1 Secondary handhole 22 EA $849.60 $18,691.20 2 Stub up 36 EA $114.00 $4,104.00 communication conduit 3 Segmental block 85 SF $37.42 $3,180.70 retaining wall 4 4" White 9,462 LF $1.70 $16,085.40 thermoplastic striping 5 Provide black 3 EA $1,500.00 $4,500.00 powder coated power pedestal with time clock & photocell 6 Cap and Grout 45 Lf $42.00 $1,890.00 existing waterline Total Additions $48,451.30 Delete: 274 2'x3' Telecom 30 EA $257.50 ($7,725.00) handhole 142 4" White solid type I 9,462 LF $5.78 ($54,690.36) pavement markings Total Deletions ($62,415.36) Total Revision to Contract Amount ($13,964.06) Original contract amount $4,350,190.39 Net increase in contract amount ($13,964.06) Previously approved changes $116,772.90 Revised contract amount $4,452,999.23 Cumulative increase in TOTAL change order amount (Percentage) 2.4% Net increase in contract time of completion 0 Revised Contract time of completion 350 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. IP all ...1, SMr 1. R.commendesTb ity -tineer Date A mil. 1., i'L-- Agreed to by Co, ..tor Date )1_,,g-4' 9 i.L__ Accepted . City Date