ST0501-CR120516 ID Task Name Duration Start Finish ay 13,'12 i Jun 10,'12 [Jul 8,'12 Aug 5,'12 Sep 2,'12 Sep 30 '12 f Oct
T 1 SIWISITIMIFITISIW SIT IMIF1T i S
1 Phase I-EB MacArthur to Allen 56 days Wed 5/16/12 Wed 8/1/12 lIN111•1011111.11M1111119,1
2 Retaining Walls 14 days Wed 5/1-6/121- Mon 6/4/12 L -
II
3 Rail 25 days Tue 6/5/12 Mon 7/9/121
4 Removals r--- :
5 daysl Tue 6/5/12 Mon 6/11/12 i ■
- ,) cj -t- l-ri:'c
J_ --t---
5 Excavation 5 days Tue 6/12/12 Mon 6/18/12 ,
6 Lime Stabilization 7 days Tue 6/19/12 Wed 6/27/1-2-7L 7 7Z 6 ev 4^)_.e, na, wA i "/* c
7
7 Concrete Paving 5 days Thu 6/28/12 Wed 7/4/12
I 1
1 ±17tii , f:etkei ....Rpp bto Awer/ bilip,te,
8 Intersections 5 days Thu 7/5/12 Wed 7/11/12 ' 111.1 of wick h".vr_
dv'' --""
9 Driveways 5 days Thu 7/5/12 Wed 7/11/12 I ill
i E
10 Inlet Tops 5 days Thu 7/5/12 Wed 7/11/2.2.01,--*
-i
11 Sidewalks&Ramps 5 days Thu 7/12/12 Wed 7/18/12 I I ■it
84#/)1 "fOtFe "7::*- 714fie
12 Backfill 5 days Thu 7/19/12 Wed 7/25/12
-7-7 0 ti 11 4
13 Landscaping 5 days Thu 7/26/12 Wed 8/1/12
:
14 1 1- r :
I '
I-- '
15 Phase II-Allen to East End 22 days' Thu 6/28/12 Fri 7/27/12 : 11111.1111111=111111.
16 Removals
1 day, Thu 6/28/12 Thu 6/2W12 i 7
, I ■ a
17 Excavation 1 day Thu 6/28/12 Thu 6/28112 I
I- i
18 Lime Stabilization 4 days Fri 6/29/12 I Wed 7/4/12 1
■ /
19 Concrete Paving 5 days Thu 7/5/12' Wed 7/11/12 1
-1-- ■ ,
20 ' Removals 1 day Thu 7/12/12 Thu 7/12/12 l
11 ,,
Task Milestone • External Tasks Ear'.47.111:• i
Project:Project1
Date:Wed 5/16/12 Split Summary 111,1111111111.1111MIP External Milestone •
Progress Project Summary ....11.111.1111. Deadline
Page 1
ID Task Name Duration Start Finish av 13,'12 I Jun 10,'12 Jul 8,'12 1 AUg 5,'12 Sep 2,'12 Sep 30,'12 [I Oct
TISIWISlT MIF lTISIW SITIMIFIT , S
21 Excavation 1 day Thu 7/12/12 Thu 7/12/12
22 Lime Stabilization 4 days; Fri 7/13/12 I Wed 7/18/12
I
, 1
23 Concrete Paving 5 days Thu 7/19/12 Wed 7/25/12
24 Intersection 2 days Thu 7/26/12 Fri 7/27/12
, l
-I
25 Inlet Tops 2 days Thu 7/26/12 Fri 7/27/12
26 Driveways 2 days Thu 7/26/12 Fri 7/27/12
27 I—
} I
28 Phase III-WB Allen to MacArthur 64 days Thu 8/2/12 Tue 10/30/12 111111.11111•1111111111
NI,
29 Removals 5 days Thu 8/2/12 Wed 8/8/12 I
I l
30 1 Excavation 5 days Thu 8/9/12 Wed 8/15/12 I
31 Lime Stabilization
7 days I Thu 8/16/12 Fri 8/24/12
7------
i.
32 Concrete Paving 5 days Mon 8/27/12 Fri 8/31/12 I N h
*--,
33 Intersections 5 days Mon 9/3/12 Fri 9/7/12
34 Driveways 5 dayST Mon 9/3/12r Fri 9/7/12 I
I
1 i
35 Inlet Tops 5 days Mon 9/3/12 Fri 9/7/12 1 Il
36 Sidewalk&Ramps 12 days 1 Mon 9/10/12 Tue 9/25/12
1
37 Sidewalk Walls 15 days 1 Wed 9/26/12 Tue 10/16/12
38 Signals 30 days Mon 9/3/12 Fri 10/12/12
39 Backfill 5 days I Wed 10/17/12 Tue 10/23/121
III
40 Landscaping 5 days Wed 10/24/12 Tue 10/30/12 I
1 SI
Task Milestone . External Tasks
Project: Project1
Date:Wed 5/16/12 Split Summary gPIMIIIIIIIMIIIIM External Milestone •
Progress Project Summary 1.1111.111111.91, Deadline
Page 2
dr'i'u2L
i Ewa■
�h
y
DAILY CONSTRUCTION REPORT
DATE S/JL PROJECT Deforest Rd
/ 2(I'Z REPORT#
-r- DAN [ NI T T F ' S S
PROJECT NO. S7 J,-01 1 L
OWNER CITY of coPPE ,L It r - i— —�FATHER j G ! ✓
'1 HIP .g --
4—_ ci 1
CONTRACTOR Tiseo facing Cmnpan■ PI11) /CY f
j 12--
Hl'1fIDIT1'
PROJECT INSPECTOR Larrc Davis
AVERAGE FIELD FORCE
NAm OI(OMIRAC-TGR SON-1IAN1:AL j 11A N1 M.-ThRP:11.4RKS -- - ----- j,
1
1 1
i VISITORS
1 1 7111E 1 REPRESENTA FIVE i REPRESENTING REMARKS
1 I
j
EQUIPMENT AT 711E SITE: --
r
(ONS1 RUC TION AC'PIVITIE5:
'': S ir ./^14)1/ 9 car 3 ' 4i " /1 —
;
1
, ip, , ,
.,
1
4
SIGNATURE
PI'MAC WORKS INSPECTOR