Steven R. Homeyer, P.E. June 5, 2012
Homeyer Engineering, Inc.
P.O.Box 294527
Lewisville, TX 75029
RE: Signature Living at Denton Creek
Construction Plan Review Comments (2°a Submittal)
The City of Coppell has reviewed the referenced plans and has the following comments to offer
Erosion control Plan -
1. Install inlet protection on Sandy Lake Rd.
The City of Coppell has reviewed the plans for the referenced addition which will be approved
with the comments above addressed.
The City of Coppell requires three sets of final construction plans for its use; your office should
submit as many additional sets for stamping as is necessary for construction operations. All
contractors and subcontractors onsite must have a copy of the plans approved by the City of
Coppell along with a copy of the City's standard construction details.
All fees must be paid prior to release of this project for construction. The City charges a 2%
inspection fee for all private construction outside the building's footprint. This includes dirt work,
paving, storm drains, water lines, sewer lines, drainage pipes, etc. that are private. For all
installations in the public right-of-way or easement, the City charges a 4% fee. A check for
inspection fees made to the City of Coppell should be submitted to this office along with the
Construction Development Permit Application and a copy of the Construction Site Notice. For
your convenience a spreadsheet is attached to the permit application for use in calculating the
inspection fees. A copy of the contract(s) should be attached for verification purposes.
If you have any questions, please contact me at your convenience.
Sincerely,
��