September 12, 2012
Dewey Bailey
RKM Utility Services, Inc.
1805 Royal Lane, Ste 107
Dallas, TX 75229
RE: Sales Tax 2010 Street Reconstruction Project—Willow Springs Drive
NOTICE TO PROCEED WITH CONSTRUCTION
Dear Mr. Bailey:
This letter will serve as your official notice to begin work on the referenced project on
October 15, 2012. One hundred eighty(175) Calendar Days were bid on this project for the
completion of work. Therefore, if work begins on October 15th, then the calendar days on
the project will expire on April 8, 2013. Your construction time will officially begin the
day of commencement or October 15th,whichever is first.
If you have any questions or need any additional information, please feel free to contact
Albert Samaniego, Construction Inspector at(972) 304-3685.
Sincerely,
George Marshall,P.E.
Civil Engineer
Office 972-304-3562
Fax 972-304-3570
gmarshal l@coppe l ltx.gov
cc: Kenneth M. Griffin, P.E., Director of Engineering&Public Works
Albert Samaniego, Construction Inspector
Glenn Hollowell, P.E., Assistant Director of Public Works