Loading...
MA1001-CS120928 T H E • C 1 T Y O F COPPELL September 28, 2012 Adrian Bowman Jim Bowman Construction Co., LP 2716 S. Rigsbee Dr. Plano, Texas 75074 RE: Notification of Repairs Needed Under Maintenance Bond—SECOND NOTICE MA 10-01 Denton Tap @ Sandy Lake Paver Replacement Dear Mr. Bowman: You were notified by letter on August 7, 2012 regarding necessary repairs to be done under the existing maintenance bond for the project. Maintenance repairs have not been done as required under the bond presented for the workmanship of the construction. It is important that these repairs take place prior to any bad weather we may have this fall and winter. 1. Pavement striping has deteriorated severely at several locations and must be replaced. Please contact me at 972-304-7090 to inform me when your crew will be on the project to correct this deficiency. I will be available to show them the areas needing attention. Sincerely, Rick O'Dell Construction Inspector cc: George Marshall, P.E., Traffic Engineer Glenn Hollowell, P.E., Asst. Director of Public Works 255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673