Coppell Ind 2-CS120927DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: PD- 185R3 -LI, Coppell Industrial Addition (Tradepoint), Lot 2, Block A, a
zoning change request from PD- 185R -LI (Planned Development -185 Revised -
Light Industrial) to PD -185R3 -Light Industrial (Planned Development -185
Revision 3 -Light Industrial), to establish a Detail Site Plan for a 1,077,716 -
square -foot office /warehouse building on 53.4 acres of property located on the
north side of West Bethel Road, between Royal Lane and Freeport Parkway at
the request of Hillwood Investments Properties, being represented by Lee
Rader, Macgregor Associates Architects.
STAFF REP.: Marcie Diamond PROJECT ID# PD -12 -0045
MC DATE: September 27, 2012 and October 4, 2012
rCONTACT: Michael Garza, P.E., Civil Engineer, 972 - 304 -7019
OMMENT STATUS: ✓PRELIMINARY FW4b RE P UD
4, VTT.'7? 9 7
1. There may be additional comments during detailed engineering plan review.
2. Loop the water line and make private by adding vaults with meters and DDC's.
3. The domestic line should come off of the public main and not the fire line.
4. Add a remote FDC to the fire line.
5. A left turn lane will need to be constructed in the Bethel Rd. median with this
project.
6. Show the driveways across Bethel from the proposed driveways.
7. Label the fire lane on the site plan.
8. Include stamped concrete in the driveway entrance.
9. Show the existing medians in Bethel Rd. properly.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: Coppell Industrial Addition (Tradepoint), Lot 2, Block A, Final Plat, being
a final plat of Lot 2, Block A, to establish necessary fire lane and utility
easements for the development of a 1,077,716- square -foot office /warehouse
building on 53.4 acres of property located on the north side of West Bethel
Road, between Royal Lane and Freeport Parkway at the request of Kerry
Roetzel, Hillwood Investments Properties.
STAFF REP.: Marcie Diamond PROJECT ID# FP -12 -0046
DRC DATE: September 27, 2012 and October 4, 2012
CONTACT: Michael
COMMENT STATUS:
P.E., Civil Engineer, 972 - 304 -7019
!"PRELIMINARY F4,VAL
1. There may be additional comments during detailed engineering plan review.
2. If the easements were dedicated by separate instrument, they will have to be abandoned
by separate instrument.
3. Include utility easements for the vaults.
4. The drainage /detention easement should be labeled as private.
5. Label the fire lane easement around the building and the width
6. Add easements for the vaults.
7. The site plan and plat NE bearing distance do not match.
2.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: Connell Industrial Addition (Tradenoint), Lot 2, Block A, Final Plat, being
a final plat of Lot 2, Block A, to establish necessary fire lane and utility
easements for the development of a 1,077,716 - square -foot office /warehouse
building on 53.4 acres of property located on the north side of West Bethel
Road, between Royal Lane and Freeport Parkway at the request of Kerry
Roetzel, Hillwood Investments Properties.
STAFF REP.: Marcie Diamond PROJECT ID# FP -12 -0046
DRC DATE: September 27, 2012 and October 4, 2012
[CONTACT: Michael Garza, P.E., Civil Engineer, 972 - 304 -7019
COMMENT STATUS: PRELIMINARY +"FINAL
AFTER "
1. There may be additional comments during detailed engineering plan review.