Subject: Southern Belle - Monthly Invoice & Progress Report
Mike,
I'm attaching our invoice for work completed through 10/19/12. Here's a
progress report on where we're at. We're on track to have 30% design
completed by 11/2, and are looking at making our 60% submittal in early
December. If you have any questions, please give me a call. Thanks!
Work Completed Last Period (9/11/12-10/19/12)
* Boundary & Topo Survey Work Completed
* Checked Survey and Created Base Files
* Set horizontal alignment and ran existing ground profiles and
cross-sections
* Started conceptual design
Work Ancipated for Current Period
* Conceptual roadway design (proposed profile & cross sections)
* Preliminary drainage analysis
* Preliminary utility (water and sanitary sewer) design
* 30% Design Review Meeting w/ City
Items Requiring Assistance from City
* We'd like to meet with you the week of Nov 5 to review the
conceptual design and discuss any design issues (if any) before
proceeding with the Preliminary Design Submittal
* Results of Storm Sewer System Condition Assessment
Kevin Shepherd, PE, ISI ENV-PV
Principal
VERDUNITY
214-425-6720
www.verdunity.com <http://www.verdunity.com/>