Carter Phase 2-CS 971208 ~ /~-~, The City With A Beautiful Future
December 8, 1997
Robert L. Wright, P.E.
Needham Wright Engineers, Inc.
10290 Monroe Dr., Suite 30S
Dallas, TX 75229
RE: Carter Addition, Phase II
Development Fee Assessment
Dear Mr Wright:
Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with a copy
of the Development Fee calculations for the referenced development.
Please make payment to the City of Coppell in the amount of $15,200.00 and forward to the
Finance Department along with a copy of the Fee Assessment table. This amount is a portion
of the assessed fees which need to be paid prior to Council approval. Please refer to attached
table for additional fees. Also provide a copy of the Engineer's estimate or contract to our office
so thc construction inspection fee can bc verified.
Providing a copy of your paid receipt to the Engineering Department will help us to verify the
payment of required fees and insure a successful beginning of this project. We look forward
to working with you on this project. If you have any questions, please contact me.
Sincerely, t~
Director of Engineering & Public Works
cc: Jennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Public Services
Greg Jones, Chief Building Official
Gary Sims, Dir. Leisure Services
DEVELOPMENT FEE WORKSHEET
PROJECT: Carter Addition, Phase H
DATE: 12/8/97
Water Impact Fee:
Domestic Meter(s): 5 - 5/8 inch X 3/4 inch 5 ESU's
Irrigation Meter(s): ESU's
ESU's
Fireline Meter(s): ESU's
Total #: 5 ESU's @ $450.00 ea. $2,250.00
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total 8: 5 Connections @ $50.O0 ea. 8250.O0
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Water Meter Fee (Domestic):
Total #: § Domestic Meter(s) @ 824.14 8120.70
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Water Meter Fee (Irrigation/Fireline):
Total #: 0 Irrigation Meter(s) @ 80.00
Total #: 0 Additional Irrigation Meter(s) @ 80.00
Total #: 0 Fireline Meter(s) @ 80.00
(100% due prior to issuance of water meters)
Water Meter Deposit Fee (Domestic):
Total #: 5 Meter(s) @ 830.00 ea. 8150.00
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 0 Meter(s) @ 835.00 ea. 80.00
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU' 5 @ 8450.00 ea. 82,250.00
Wastewater Tap Inspection Fee:
Total #: 5 Connections @ 850.00 ea. 8250.00
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 5 Lots @ 850.00 ea. 8250.00
(100% due prior to issuance of building permit)
Page 1
DEVELOPMENT FEE WORKSHEET
Park Fee (For Resdential Developments Only):
* Preliminary plat approved prior to June 23, 1992:
N/A Single-family @ $150.00 / Lot N/A
N/A Multi-family @ $75.00 / Unit N/A
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after June 23, 1992:
N/A Single-family @ $350.00 / Lot N/A
N/A Multi-family @ $350.00 / Unit N/A
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after October 26, 1993:
5 Single-family @ $1285.00 / Lot $6,425.00 __.
N/A Multi-family @ $1285.00 / Unit N/A
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations) $4,275.00
Street Lighting Fees: Information not
Assessed for lighting in the City's right-of-way, available at this time
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees: Information not
Assessed for signage in the City's right-of-way, available at this time
(See attached fee calculations if applicable)
Construction Inspection Fees: Need submittal of
A copy of the development contract must be submitted for assessment, development contracts
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Page 2
DEVELOPMENT FEE TABLE
Project: Carter Addition, Phase H
Date: 12/8/97
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $2,250.00 $2,250.00
(100% due prior to Council Approval)
Water Tap Inspection Fcc $250.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $120.70
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) '. $0.00
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $150.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $0.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $2,250.00 $2,250.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $250.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $250.00
(100% due at Issuance of Building Permit)
Park Fee $6,425.00 $6,425.00
(100% due prior to Council Approval)
Roadway Impact Fee $4,275.00 $4,275.00
(100% due prior to Council Approval)
Street Light Fee Information not
(100% due prior to Acceptance of Project available at this time
Street Sign Fee Information not
(100% due prior to Acceptance of Project available at this time
Construction Inspection Fee Need submittal of
development contracts
TOTAL $16,220.70
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $15,200.00
ROADWAY IMPACT FEE CALCULATIONS
PROJECT: Carter Addition, Phase H
DATE: 12/8/97
ROADWAY IMPACT FEE:
Service Area * 6 I
Category ** Residential
I
Land Use ** Single-Family Detached
Building Size (Sq. Ft.) N/A
Development Units ** 5
Vehicle Miles per Development Unit ** 2.85
I
Fee per Vehicle Mile *** $300 [
Roadway Impact Fee due = (Development Units) x
[(Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) = $4,275.00
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)