Tax 2011B-CN121106 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Vanbebber Drive-Tax 2011B CONTRACTOR: CPS Civil,LLC OWNER: City of Coppell CHANGE ORDER NO.: One(1) DATE: November 2,2012 1.This change order provides for the abandonment of an existing water valve,and a new connection to the 16"water line in Denton Tap. This work is necesarry due to the age and condition of the existing valve. This change includes all necesarry materials, labor,and equipment to complete this additional work. Item Description Quantity Unit Unit Price Total ADD: 1 16'x 8"Tapping Sleeve and 1 LS $8,275.00 $8,275.00 Valve Total Additions $8,275.00 Total Deletions $0.00 Total Revision to Contract Amount: $8,275.00 Original contract amount $588,100.00 Net increase in contract amount $8,275.00 Previously approved changes $0.00 Revised contract amount $596,375.00 Cumulative increase in TOTAL change order amount(Percentage) 1.4% Net increase in contract time of completion 2 Revised Contract time of completion 122 Calendar Days CITY OF COPPELL CHANGE OR EXTRA WORK ORDER The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord 11- • Iy R o ende b ity Engineer Date 0 Z_1/4.©/' Agreed to by Contr.%I r? Date /////L Acce• -d by City Date