November 6, 2012
Robert Caudill
Tiseo Paving Company
PO Box 270040
Dallas Texas 75227-0040
RE: Project#ST 05-01,Deforest Road Reconstruction
Completion of Project
Dear Mr. Caudill:
This letter is an official notification to your company that contract time for this project has been
exceeded. The Notice to Proceed With Construction letter dated December 13, 2011 served as "your
official notice to begin work on the referenced project on January 9, 2012. For purposes of the contract, your
calendar days will start on that date. Three hundred (300) Calendar Days were bid on this project for
completion of work. Therefore, we anticipate the project being complete by November 4, 2012."
This notification is a reminder and is written to bring to your attention the provision in the contract
allowing for a $1,000 per day penalty for late completion. Penalties began as of November 5, 2012 and
will continue to accumulate at $1,000 per day until final completion and acceptance of the project is
achieved. If you have questions or need clarification of this provision, feel free to call me or contact Larry
Davis at 469-576-7707.
Sincerely,
Georg- arshall,P.E.
Traffic Engineer
Office: 972-304-3562
gmarshall@coppelltx.gov
cc: Kenneth Griffin,P.E.,Director of Engineering&Public Works
Larry Davis, Construction Inspector