Loading...
ST0501-CN121207 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: ST05-01 Deforest Road CONTRACTOR: Tiseo Paving,Inc. OWNER: City of Coppell CHANGE ORDER NO.: 2 DATE: 12/3/2012 Item Description Quantity Unit Unit Price Total ADD: 216 Remove&Salvage Fire Hydrant 1 EA $275.00 $275.00 509 Install Fire Hydrant and Valve 1 EA $5,000.00 $5,000.00 Assembly 512 Furnish and Install New 1"Water 7 EA $2,500.00 $17,500.00 Service New Adjust Grate Inlet at Sta 25+18.03 1 LS $1,200.00 $1,200.00 New Paint Bridge Rail 550 LF $36.25 $19,937.50 SUBTRACT: 511 10"Water main lowering at paving -1.0 LS $15,000.00 -$15,000.00 Sta 25+75 Total Revision to Contract Amount $2$;V12.50 Original contract amount $2,096,463.73 Prior Change Order Amounts $19,183.50 Net increase in contract amount $28,912.50 Revised contract amount $2,144,559.73 Cumulative increase in TOTAL change order amount(Percentage) 2% Net increase in contract time of completion 0 Revised Contract time of completion 300 The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. R ommended City Engineer Date Agree. to by Contractor D. e Accept by City Date