Chaucer-CS 921204
P ~~ Box 478
Ccppell. Texas 75019
L? µ-4b2-0(122
December 4, 1992
Mr. Gregory L. Rich
Siepiela Interests, Inc.
5001 LBJ Freeway, Ste. 830
Dallas, TX 75244
RE: Walk-Through
Chaucer Estates
Dear Greg:
Please be advised that awalk-through has been scheduled for Wednesday, December 9, 1992
at 9:00 a.m. for the water, sanitary sewer, paving and drainage facilities in the referenced
project.
Please ensure that all facilities are clean and accessible at that time and that contractor's
representatives are present to assist with the inspection.
Your cooperation in this effort is greatly appreciated. If you should have any questions, please
call at your earliest convenience.
Sincerely,
----.. _
arret Campbell
Construction Inspector
cc: Howard Pafford, Water Superintendent
Rey Gonzales, Street Superintendent
Bill Anderson, Dan Dowdey & Associates
Austin Paving
Legend Construction
chautwl l
1
UNZICKER SCHNUABUSCH
8 ASSOCIATES INCORPORATED
CIVIL ENGINEERS•SURVEYOFS•PLANNEPS
December 4, 1992
Mr. Ken Griffin, P.E.
City of Coppell
Engineering Department
P.O. BoX 478
Coppell, Texas 75019
RE: CHAUCER ESTATES
91001-0
Dear Mr. Griffin:
I have been informed by the paving contractor for this development
that final cleanup at the site will be completed by Tuesday, December
8, 1992. Therefore, I request that the City of Coppell perform a
walk-through for final acceptance of the project. Please call me at
634-3300 to schedule a convenient time for the walk-through.
Thank you for your time and cooperation in this matter. I look
forward to working with you toward a successful completion of this
project.
Sincerely,
_. .C.
Craig S. S ley, .E.
Project Manager
CSS/nj
CC: Garreth Caiilpbell/City of Coppell
Greg Rich/S'epiela Interests, Inc.
i
~ , z ~$
C,~,
8700 STEMMDNS FREEWAY SUITE FOUR HUNDRED DALLAS TEXAS 15247 214.634.3300 FAX 214.634.3338
PAUL S. UNZICKER, PE. DAVID M. SCHNURBUSCH, P.E. KEVIN RAY KENDRICK, P.E. DAVID F. McCULLAH, R. P.L. S.
President Vice President Project Manager • Associate Survey Manager • Associate