WA9601-CS 980115SII~K, JACOBS & FINKLEA, L.L.P. ProjectNo. 96149
CONSULTING ENGINEERS G I -- 2 ~ - 9 8 p 0 4: l 9 I s
Client: City of Coppell, Texas Page No. 1 of 1
Project: Wagonwheel Ranch Park Date: January 15, 1998
2.0 M.G. Elevated Storage Tank By: PAC
ENGINEER'S OPINION OF CONSTRUCTION COST- BASE BID
Item No. I Description I Quantityl Unit [ Price I Amount
1 2.0 M.G. Elevated Storage Tank and All Appurtenances 1 L.S. $2,000,000.00 $2,000,000.00
2 24" RCCP Waterline Including All Appurtenances 292.31 L.F. $100.00 $29,231.00
3 12" Waterline Including All Appurtenences 66.26 L.F. $45.00 $2,981.70'
4 18" RCP Storm Sewer 20 L.F. $40.00 $800.00
5 24" RCP Storm Sewer 188.50 L.F. $65.00 $12,252.50
6 CH-11A Headwall 6.34 C.Y. $1,000.00 $6,340.00
7 CH-11B Headwall 3.61 C.Y. $1,000.00 $3,610.00
8 3'X3' Grate Inlet Including Rip-Rap, 1 EA. $3,000.00 $3,000.00
9 3'X3' Drop Inlet 1 EA. $2,500.00 $2,500.00
10 6-Inch Reinforced Concrete Pavement (Parking &Drive) 2,981 S.Y. $20.00 $59,620.00
11 6-Inch Monolithic Curb (Parking &Drive) 182.50 L.F. $5.00 $912.50
12 Lime Treated Subgrade 3,155.50 S.Y. $5.00 $15,777.50
13 Lime 50.50 TONS $100.00 $5,050.00
14 Material Storage Bins Exterior Wall 149.70 C.Y. $400.00 $59,880.00
15 Brick Veneer Wall with Brick Columns 601 L.F. $240.00 $144,240.00
16 Welded Steel Fence 216 L.F. $130.00 $28,080.00
17 Landscaping and Irrigation System 1 L.S. $33,800.00 $33,800.00
Base Bid Total: $2,408~075.20
1:Xcoppel 1~96- ] 49XLXdesi~n\eng-est_wk4
SHIMEK, JACOBS & FIN~j_~EA, L.L.P. ProjectNo. 96149
CONSULTING ENGINEERS o 1.-22-.-9 ~ P{~4: 19 I t~
Client: City of Coppell, Texas Page No. 1 of 1
Project: Wagonwheel Ranch Park Date: January 15, 1998
2.0 M.G. Elevated Storage Tank By: PAC
ENGINEER'S OPINION OF CONSTRUCTION COST ALTERNATES A & B
Item No. ~ Description i Quantity ~ Unit ~ Price I Amount
Additive Alternate A
I 6-Inch Reinforced Concrete Pavement (Northpoint Drive) 1,963 S.Y. $20.00 $39,260.00
2 :6-Inch Monolithic Curb 1,205.50 L.F. $5.00 $6,027.50
3 Lime Treated Subgrade 2,125 S.Y. $5.00 $10,625.00
4 Lime 34 TONS $100.00 $3,400.00
5 Unclassified Street Excavation 177 C.Y. $5.00 $885.00
6 Type III Barricade 5 EA. $300.00 $1,500.00
Alternate A Total: $61,697.50
Additive Alternate B
1 6-Inch Crushed Stone Pavement (Northpoint Drive) 380 S.Y. $20.00. $7,600.00
2 Unclassified Street Excavation 72 C.Y. $5.00 $360.00
3 Type III Barricade 1 EA. $300.00 $300.00
I
Alternate B Total: $8,260.00
Base Bid + Alternate A Total: $2,469,772.70
Base Bid + Alternate B Total: $2,416,335.20
J:Xcoppell~96-149~L~tesign~ng~stwk4
""' T 01-22--p8 P04:20 IN
NOTICF_, TO BIDDF_,I~
CITY OF COPPELL, TEXAS
WAGON WHEEL RANCH ELEVATED STORAGE TANK
The City of Coppell is accepting bids for the 2.0 Million Gallon Wagon Wheel Ranch Elevated Storage
Tank (AWWA D100). In addition to the elevated tank, the project includes approximately 1,963 square
yards of 6-inch reinforced concrete pavement, 292 linear feet of 24-inch watefiine, 2,981 square yards of
reinforced concrete material storage area, 150 cubic yards reinforced structural material storage bin walls,
along with all necessary appurtenances. Sealed bids addressed to the Purchasing Agent, City of Coppell,
Texas, for Wagon Wheel Ranch Elevated Storage Tank will be received in the Purchasing Office at the
City of Coppell Town Center, 225 Parkway Boulevard, until 2:00 p.m. on February, 19, 1998, and then
publicly opened and read aloud. Each Bidder shall submit two identical copies of this bid with the City
of Coppell Bid No. Q0198-03, designated clearly on the exterior of the bid envelope.
A Pre-Bid Conference is scheduled for February 15, 1998 at 2:00 p.m., at the City of Coppell's Town
Center. Attendance to the Pre-Bid Conference is not mandatory to bid.
Proposals shall be accompanied by a cashier's or certified check upon a national or state bank, or savings
and loan in an amount not less than five percent (5%) of the total maximam bid price, payable without
recourse to the City of Coppell, or a bid bond in the same amount from a reliable surety company, as a
guarantee that the bidder will enter into a contract and execute performance bond and payment bond
within ten (10) days after notice of award of contract to him. The notice of award of contract will be
given by the Owner within ninety (90) days following the opening of bids.
The successful bidder must furnish performance bond upon the form provided in the amount of 100
percent of the contract price and a material and labor payment bond upon the form provided in the
amount of 100 percent of the contract price from an approved surety company holding a permit from the
State of Texas to act as surety, or other surety or sureties acceptable to the Owner.
The Owner reserves the fight to reject any or all bids and to waive formalities. Unreasonable or
unbalanced unit prices will be considered sufficient cause for rejection of any bid or bids. NO BID
TRANSMITTED BY FAX WILL BE ACCEPTED.
Bidders are expected to inspect the site of the work and to inform themselves regarding local conditions
and conditions under which the work is to be done.
Complete sets of bidding documents must be used in preparing Bids; the City of Coppell assames no
responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding
Documents.
Plans, specifications and bidding documents may be purchased from the office of Shimek, Jacobs &
Finklea, L.L.P., Consulting Engineers, 8333 Douglas Avenue, Suite 820, Dallas, Texas 75225, for the sum
of Seventy-Five Dollars ($75.00) per set.
J:\Coppell~96149xspecs\Sec-I .doc l -2
"" CITY OF COPPELL, TEXAS '~'
WAGON WHEEL RANCH ELEVATED STORAGE TANK
01-22-9 8 P04: 20 I N
Tank Contractors & Publishers
Publisher/
Contractor Address City State Zip Phone/Fax Supplier
Associated General Contractors 6220 N. Belt Line, #210 Irving Texas 75063 Publisher
CBI Na-Con, Inc. P.O. Box 41146 Houston Texas 77241-1146 713-466-1226 Prime
Fa,: 713-466-1259
Dodge Reports 1341 W. Mockingbird Lane, Dallas Texas 75247 214-630-6111 Publisher
#200-East Fix: 214-688-4324
Landmark Structures, Inc. 1665 Harmon Road Fort Worth Texas 76177 817-439-8888 Prime
Fl,: 1-817-439-9001
PDM, Inc. (Pitt-Des Moines, Inc.) 175 TownPark Drive, #240 Kennesaw Georg 30144 1-770-420-9191 Prime
ia F,,: 1-770-420-9155
Texas Contractors 2510 National Drive Garland Texas 7504 ! 972-27 ! -2693 Publisher
h,: 972-278-4652
Whitley & Siddons P.O. Box 821773 Dallas Texas 75382 214-343-8878 Publisher
v,x: 214-343-4303
Thursday, January 22, 1998 Page 1
SHIMEK, JACOBS & FINKLEA, L.L.P.
CONSULTING ENGINEERS
........................................ i8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900
u1-22-98 P04:18
ROSS L. JACOBS, P.E.
RONALD V. CONWAY, P.E.
JOHN W. BIRKHOFF, P.E.
JOE R. CARTER, P.E.
GARY C. HENDRICKS, P.E.
~. c. nN}ct.zA, P.z. January 22, 1998
Mr. Kenneth M. Griffin, P.E.
City of Coppell
Post Office Box 478
Coppell, Texas 75019
Re: Wagon Wheel Ranch
Elevated Storage Tank
Dear Mr. Griffin:
We are enclosing two sets of final plans and specifications for the Wagon Wheel Ranch Elevated Storage
Tank project. Our opinion of probable construction cost based on the final plans and specifications is in the
range of 2.4 million dollars. An itemized copy of our opinion of probable cost is enclosed for your review.
We are also enclosing a copy of the notice to contractors and a listing of the contractors who perform this type
of work. We will notify these contractors and publishers directly. As we discussed, the first advertisement
should be published in the local newspaper no later than Friday, January 30, 1998.
We are available to discuss this project further at your convenience.
Sincerely y, u
Enclosure