Tax 2011B-CN130128 CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Vanbebber Drive-Tax 2011B
CONTRACTOR: CPS Civil,LLC
OWNER: City of Coppell
CHANGE ORDER NO.: Two(2) DATE: January 28,2013
1. This change order provides for the inspection and repair of the existing storm drain collection main
within Vanbebber Drive. This change includes all necesarry materials, labor,and equipment to complete
this additional work.
2. This change order provides additional time to complete the necesarry repairs.
Item Description Quantity Unit Unit Price Total
ADD: 1 Television inspection of
existing storm drain 1,200 LF $1.15 $1,380.00
Over excavate and
2 recompact trench line of 1 LS $8,446.00 $8,446.00
storm drain
3 Grout and patch interior of 1 LS $2,985.00 $2,985.00
storm drain
Total Additions $12,811.00
Total Deletions $0.00
Total Revision to Contract Amount: $12,811.00
Original contract amount $588,100.00
Net increase in contract amount $12,811.00
Previously approved changes $8,275.00
Revised contract amount $609,186.00
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Cumulative increase in TOTAL change order amount(Percentage) 3.6%
Net increase in contract time of completion 14
Revised Contract time of completion 136 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and
z.C1 •13
R commende by City Engineer Date
O/A
Agreed to by Contractor Date
//2,Y/4
7.7c7A by City Date