Tax 2011B-CN130128 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Vanbebber Drive-Tax 2011B CONTRACTOR: CPS Civil,LLC OWNER: City of Coppell CHANGE ORDER NO.: Two(2) DATE: January 28,2013 1. This change order provides for the inspection and repair of the existing storm drain collection main within Vanbebber Drive. This change includes all necesarry materials, labor,and equipment to complete this additional work. 2. This change order provides additional time to complete the necesarry repairs. Item Description Quantity Unit Unit Price Total ADD: 1 Television inspection of existing storm drain 1,200 LF $1.15 $1,380.00 Over excavate and 2 recompact trench line of 1 LS $8,446.00 $8,446.00 storm drain 3 Grout and patch interior of 1 LS $2,985.00 $2,985.00 storm drain Total Additions $12,811.00 Total Deletions $0.00 Total Revision to Contract Amount: $12,811.00 Original contract amount $588,100.00 Net increase in contract amount $12,811.00 Previously approved changes $8,275.00 Revised contract amount $609,186.00 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER Cumulative increase in TOTAL change order amount(Percentage) 3.6% Net increase in contract time of completion 14 Revised Contract time of completion 136 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and z.C1 •13 R commende by City Engineer Date O/A Agreed to by Contractor Date //2,Y/4 7.7c7A by City Date