Castlebury-CS 990812August 12, 1999
P.O. Box 478
Coppell, Texas 75019
972-462-0022
ILE
Mark Gaines
Ryland Homes
Three Metro Square
12200 Ford Road, Suite 400
Dallas, Texas 75234
Castlebury Court f
Final Acceptance
Dear Mark Gaines:
A final inspection of paving and utilities for the referenced project has been confirmed by
representatives of the City of Coppell.
The two-year maintenance bonds and as-built drawings have been received from the contractor.
Maturity on the bonds will be two years from the date of this letter. Maturity on the Erosion
Control Bond will also be two years from the date of this letter.
Cons~ ~ction In~ector
cc: Bill Jones, Jr., Site Concrete
David Gregory, Goodwin & Marshall
Mike Martin, Assistant City Engineer
Doug Stevens, Engineering Technician
Glenn Hollowell, Director of Public Works
Greg Sones, Chief Building Official
Travis Crump, Fire Marshal
Procker/subdivsn/Olfmals/castlbry