ST0003-CN090427CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Coppell Road Project # ST 00 -03 CONTRACTOR: Tiseo Paving Company OWNER: City of Coppell CHANGE ORDER NO.: Three (3) DATE: April 27, 2009 Pg 1 of 2 ADD: Item Description 1. Concrete Encase Sewer @ 48" RCP 2. Stack Block Pavement Wall (430 SF @ $33.10 /SF) Total Revision to Contract Amount Quantity Unit Unit Price Total 1 LS $822.80 $822.80 430 SF $33.10 $14,233.00 $15,055.80 CHANGE ORDER NO.: Three (3) Previous contract amount Net increase in contract amount Change Order #1 Net increase in contract amount Change Order #2 Net increase in contract amount Change Order #3 Revised contract amount Net increase in contract time of completion Contract time of completion Pg 2 of 2 $2,857,846.30 $21,565.50 $11,511.50 $15,055.80 $2,905,979.10 10 375 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Recommended by Uty Engineer Date Agre d to by Contractor Date Ae� &,/ ay Accepte y City bate' (4/16/2009) Keith Marvin - RE: RE: Pavestone products From: 'Robert Caudill' <rcaudill @Tiseo Paving. com> To: "Keith Marvin" <kmarvin @ci.coppell.tx.us> Date: 4/9/2009 7:25 AM Subject: RE: RE: Pavestone products Keith; The revised price for the retaining wall is $33.10/SF. Robert Caudill Vice President Tiseo Paving Company (972) 289 -0723 - - - -- Original Message---- - From: Keith Marvin [ mailto :kmarvin @ci.coppell.tx.us] Sent: Wednesday, April 08, 2009 1:58 PM To: Robert Caudill Subject: Fwd: RE: Pavestone products Robert, For your use in pricing the Coppell Road retaining wall. Please price the River Red. Keith Marvin, P.E. Project Engineer (972) 304 -3681 q 30 >>> Bonnie Busboom <bbusboom @coppellisd.com> 4/8/2009 10:14 AM >>> River Red, sorry. - - - -- Original Message---- - From: Keith Marvin [ mailto :kmarvin @ci.coppell.tx.us] Sent: Thursday, April 02, 2009 8:34 AM To: Bonnie Busboom Subject: Pavestone products Bonnie, Attached is the color sheet for the Pavestone wall product. Please let me know if you think this product would work for you. Thanks, Keith Keith Marvin, P.E. Project Engineer (972) 304 -3681 L 93 Page 1 PAVING COMPANY P.O. Box 270040 Dallas, Texas 75227 -0040 Telephone (972) 289 -0723 Fax (972) 216 -5637 April 10, 2009 Keith Marvin, P.E. City of Coppell 255 Parkway Coppell, Texas 78019 Re: Coppell Road ST 00 -03 Concrete Encase Sewer @ 48" RCP Mr. Marvin, Please see the attached request for additional work. We have attached a breakdown from North Texas Contracting for your review. An additional 10% for Tiseo Paving Co. is requested below. NTC $ 748.00 TISEO10% 74.80 TOTAL $ 822.80 Sincerely Lance Smith Project Administrator 644W,i " 1974 CONCRETE ENCASE SEWER @ 48" RCP CROSSING AT STATION 8 +63.35 COPPELL ROAD CITY OF COPPELL / TISEO PAVING NORTH TEXAS CONTRACTING NTC LABOR (4 MAN CREW FOR 2 HOURS) SUBTOTAL LABOR $ 194.75 EQUIPMENT REGULAR REGULAR OT OVERTIME TOTAL SUPERVISORS TRUCK HOURS RATES HOURS 9.08 RATES 9.08 LABOR HR CHARGED $ CHARGED $ ADDED TRACK EXCAVATOR AMOUNT SUPERINTENDENT (50 %) 1.0 $ 33.75 0 $ 50.63 $ 33.75 FOREMAN 2.0 $ 25.50 0 $ 38.25 $ 51.00 OPERATOR (1) 2.0 $ 16.00 0 $ 24.00 $ 32.00 PIPE LAYER (1 ) 2.0 $ 14.00 0 $ 21.00 $ 28.00 PIPE HELPER (2) 4.0 $ 12.50 0 $ 18.75 $ 50.00 SUBTOTAL LABOR $ 194.75 EQUIPMENT SUPERVISORS TRUCK HR 1 $ 9.08 $ 9.08 FOREMANS TRUCK HR 2 $ 9.08 $ 18.16 TRACK EXCAVATOR HR 0 $ 93.65 $ - CASE 580 HR 0 $ 63.65 $ - LOADER 2YD HR 0 $ 81.22 $ - SKID STEER HR 0 $ 54.93 $ - GENERATOR HR 0 $ 24.58 $ - COMPACTOR ( RIDE ON 54 -) HR 0 $ 28.61 $ - ROAD PLATE RENTAL HR 0 $ 17.00 $ - DAILY SAFETY ITEMS/ PPE / CONSUMABLE$ HR 2 $ 7.50 $ 15.00 SUBTOTAL EQUIPMENT $ 42.24 MATERIALS & SUBCONTRACTORS UNIT QUANTITY UNIT PRICE TOTAL CONCRETE MATERIAL CY 3 $ 105.00 $ 315.00 SUBTOTAL MATERIALS & SUBS $ 315.00 TOTALS TOTAL SUB & MAIL COSTS LS 1 $ 315.00 $ 315.00 TOTAL EQUIPMENT LS 1 $ 42.24 $ 42.24 TOTAL LABOR LS 1 $ 194.75 $ 194.75 TOTAL NTC COST $ 551.99 BURDEN ON LABOR A. 0.425 $ 194.75 $ 82.77 OVERHEAD % 0.10 $ 634.76 $ 63.48 PROFIT % 0.05 $ 698.23 $ 34.91 NTC BONDING ADJUSTMENT % 0.02 $ 733.15 $ 14.66 TOTAL: $ 747.81 SAY: $ 748.00 NOTES PLEASE ADD 112 DAY TO CONTRACT FOR CHANGE