ST9902-CN070626CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: West Sandy Lake Road Project # ST 99 -02A
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
CHANGE ORDER NO.: Seven (7) DATE: June 26, 2007
Item Description Quantity Unit
Unit Price Total
ADD: T -29 Traffic Signal Foundations 16 LF
180.00 $2,880.00
Increase Poles P -4 foundations
to 36"
New Install a second set of anchor 2 LS
550.00 $1,100.00
bolts per foundations
Total Revision to Contract Amount Change Ord. #7
$3,980.00
Original contract amount
$3,961,787.00
Net increase in contract amount Change Order # 1 5/9/06
15,635.00
Net increase in contract amount Change Order # 2 5/17/06
2,900.00
Net increase in contract amount Change Order # 3 11/2/06
6,737.00
Net increase in contract amount Change Order # 4 1 /8/07
2,250.00
Net increase in contract amount Change Order # 5 2/15/07
2,090.00
Net increase in contract amount Change Order # 6 4/18/07
1,755.00
Net increase in contract amount Change Order # 7 6/26/07
3,980.00
Revised contract amount $3,997,134.00
Net increase in contract time of completion 2 Day
Revised Contract time of completion 312 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
Page 1 of 2
Recommended
Ace
6, �Lb
ffin, P.E., City Engineer Date
im Witt, City Manager Date
Agreed to by Tiseo Paving Company
Date