Sales Tax 09-CS100827 (2)August 27, 2010
Mr. Keith Marvin, P.E.
City of Coppell
255 E. Boulevard
Coppell, Texas 75019
Re: S. Heartz Road & Clear Creek Lane
Coppell, Texas
Engineering Inspection & Testing Services
AGG Proposal No: P10 -0828C
Dear Mr. Marvin:
• GEOTECHNICAL ENGINEERING
• ENVIRONMENTAL CONSULTING
• CONSTRUCTION MATERIALS ENGINEERING AND TESTING
Phn: (972) 304 -3681
Fax: (972) 304 -3570
Alliance Geotechnical Group (AGG) is pleased to confirm our firm's interest in providing
materials inspection and testing services for the proposed S. Heartz Road and Clear Creek
Lane project noted above. A schedule of unit fees for this project is attached.
After reviewing our fee schedule if you have any questions, please contact the undersigned at
(972) 444 -8889. If acceptable, please sign below and fax back to our office as our Authorization
to Proceed. We look forward to the opportunity of working with you on this project.
Respectfully submitted,
ALLIANCE GEOTECHNICAL GROUP
Roe Nance, n 0ip
Sr. Project Manager
Approved by:
Si atur
Date:
MEMBER 3228 Halifax Street • Suite A • Dallas, Texas 75247
Tel: 972-444-8889 • Fax: 972 -444 -8893 • www.aggengr.com
SCHEDULE OF FEES
FOR
CONSTRUCTION MATERIALS ENGINEERING & TESTING
S. HEARTZ ROAD & CLEAR CREEK LANE COPPELL, TEXAS AGG PROPOSAL NO.: P10 -0828C
DESCRIPTION OF SERVICES
QUANTITY
@
UNIT FEE
UNIT
FEE
A. MASS GRADING, LIME AND WALL BACKFILL TESTING & INSPECTION
23
@
$13.00
• Moisture /Density Relationship of Soils (ASTM D -698)
4
@
$150.00
each
$600.00
• Atterberg Limits
4
@
$50.00
each
$200.00
• Lime Series ( 5 point PI method)
2
@
$225.00
each
$450.00
• Cement Series ( as needed)
$299.00
@
$375.00
each
$0.00
• Sulfate Test
4
@
$90.00
each
$36000
• Driveway Subgrade Density Test ( 1 per driveway)
18
@
$13.00
each
$234.00
• Sidewalk Density Tests ( 1 per 300 If)
23
@
$13.00
each
$299.00
• Barrier Ramp Density Tests ( 1 per ramp)
14
@
$13.00
each
$182.00
• Lime Gradation Test (1 per 300 If)
23
@
$13.00
each
$299.00
• Lime Depth Verification (1 per 300 If)
23
@
$13.00
each
$299.00
• Lime Subgrade In -Place Density Test (1 per 300 If)
23
@
$13.00
each
$299.00
• Retaining Wall Backfill Density Test (1 per lift)
4
@
$13.00
each
$52.00
• Sr. Engineering Tech to perform testing
148
@
$37.00
hour
$5,476.00
• Project Manager
5
@
$75.00
hour
$375.00
• Geotechnical Project Manager( as needed)
@
$90.00
hour
$0.00
• Sr. Geotechnical Engineer ( as needed)
@
$110.00
hour
$0.00
• Vehicle Charge
34
@
$35.00
trip
$1,190.00
Sub -Total
$10,315.00
B. UTILITY BACKFILL TESTING & INSPECTION
• Moisture /Density Relationship of Soils (ASTM D -698)
4
@
$150.00
each
$600.00
• Atterberg Limits
4
@
$50.00
each
$200.00
• Sieve Analysis for Embedment
2
@
$35.00
each
$70.00
• In -Place Density Test' (ASTM D2922) (1 fdt per 150 If)
164
@
$13.00
each
$2,132.00
• Concrete Test Cylinders (4 cyls per set) inlets,manholes
24
@
$14.00
each
$336.00
• Sr. Engineering Tech to perform testing
132
@
$37.00
hour
$4,884.00
• Project Manager
4
@
$75.00
hour
$300.00
• Vehicle Charge
36
@
$35.00
trip
$1,260.00
Sub -Total
$9,782760
P10 -0828C Page 2 of 3
SCHEDULE OF FEES
FOR
CONSTRUCTION MATERIALS ENGINEERING & TESTING
S. HEARTZ ROAD & CLEAR CREEK LANE COPPELL, TEXAS AGG PROPOSAL NO.: P10 -0828C
DESCRIPTION OF SERVICES QUANTITY UNIT FEE UNIT FEE
C. CONCRETE & REINFORCING TESTING & INSPECTION
• Concrete Inspection & Testing (regular time)
255
@
$37.00
hour
$9,435.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Paving
132
@
$14.00
each
$1,848.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Sidewalk
48
@
$14.00
each
$672.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Driveways
24
@
$14.00
each
$336.00
• Concrete Cylinder Test -(4 cyls per 100 cyd ) - Barrie ramps
12
@
$14.00
each
$168.00
• Concrete Core Depth Checks ( 2" dia core / 300 If)
23
@
$40.00
each
$920.00
• Project Manager
7
@
$75.00
hour
$525.00
• Vehicle Charge
63
@
$35.00
trip
$2,205.00
Sub -Total $16,109.00
ESTIMATED TOTAL $36,206.00
NOTES:
1. Overtime rates of 1.5 times the regular hourly rate will be charged for hours worked over eight (8) hours
per day Monday thru Friday or any time before 7:00 a.m. or after 5:00 p.m. Service performed on Saturdays
and Sundays will be billed at 1.5 times the regular hourly rate. Services performed on recognized holidays
will be billed at 2.0 times the regular hourly rate. ( WILL BE BILLED TO CONTRACTOR)
2. All laboratory test fees are F.O.B. our laboratory; additional charge for sample pickup may apply.
3. Any additional tests will be billed on a hourly rate and charged at the applicable rate, portal -to- portal.
4. Additional test not specified in this proposal will be quoted upon request.
5. This proposal does not include any technician stand -by, non - readiness charges, and /or trips or re -tests of the
previous failing tests.
6. The above unit rates are based on the following estimated schedule:
• Concrete paving - 10 placements estimated
• Concrete sidewalk steps - 2 placements estimated
• Barrier free ramps - 3 placements estimated
• Concrete driveways - 6 placements estimated
* Sidewalks - 12 placements estimated
* Concrete inlets - 6 placements estimated
* Lime subgrade- 12 estimated site visits
* Sidewalk subgrade - 7 estimated site visits
* Driveway subgrade - 4 estimated site visits
* Barrier free ramp subgrade - 4 estimated site visits
* Site utilities - 24 estimated site visits
Page 3 of 3
P10 -0828C