CF-Village-CS 890531 GINN, INC. CONSULTING ENGINEERS
May 31, 1989
Cajun Contractors, Inc.
P.O. Box 540487
Dallas, Texas 75354-0487 ~[~ - ~ ~ ~:
City of Coppell, Texas
Dear Mr. Hirschey:
Per your April 12, 1989 letter and our May 9, 1989 meeting, we have re-
evaluated your request for additional compensation on the drilled foundation
piers. Based on our review of the Contract Documents, plans, and inspectors
log, we are able to substantiate a total of 296.5 VLF of 18" drilled piers
above plan quantities for the 32 foundation piers. Therefore, our
recommendation to the Owner is for a Change Order in the following amount:
296.5 VLF ~ $24.25/VLF $7,190.13
Bonds & Insurance (~2%) 143.80
Subtotal $7,333.93
Cajun (15%) 1,100.07
Total Change Order $8,434.00
If you concur with the above, please sign all six (6) copies of the Change
Order and return them to our office. We will then forward them to the City of
Coppell for their consideration.
Please note that the Contract Documents require that claims of this nature be
submitted in writing within thirty (30) days of the occurrence. Future claims
that fail to me~I the required submittal deadline m~y-bc denied on tbi~s.
Sincerely,
Sanfdrd W. Case, P.E.
Project Manager
attachments
cc:Russell Doyle Steve Goram
H. Wayne Ginn, P.E. Smoky Ginn
J.R. Richardson File 380