CF-Sandy Station-CS 861117GINN, INC. ' CON: GINEERS
November 17, 1986 /g ~Or~ '
Mr. Ed Powell, City Engineer ~,_.¢.~y
P.O. Box 478
Coppell, TX 75019
Re: Sandy Lake Road Pump Station Improvements Project
Dear Mr. Powell:
A final inspection of the above referenced project was made by
representatives of Ginn, Inc. and the City of Coppell on
October 23, 1986. The mechanical and electrical appurtenances
were found in compliance with the plans and specifications.
A letter of one-year guarantee for all materials and workmanship
for this project has not been received yet. Substantial
completion of this project was July 2, 1986. The one-year
guarantee should start on the July 2, 1986 date. We recommend
final payment be issued upon our receipt of the letter of
one-year guarantee from the contractor.
Please call if you have any questions.
Sincerely,
Kevin Peiffer
/ss
cc: Steve Goram
R. E. Josserand, Onyx Const.
Wayne Ginn
Randy Fleming
16135 Prcston Road · Suite 106 · Dallas, Texas 75248 · Phone 214/386-6611