PA9601-CN970711CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Copperstone Trail Project # PA 96 -01 CONTRACTOR: Pavement Construction & Maintenance OWNER: City of Coppell CHANGE ORDER NO.: 1 DATE: 7/11/97 CHANGE OR EXTRA WORK TO BE DONE Item Description Quantity Unit Unit Total Price ADD: 1 Addition to Trail 124 LF 85.00 $10,540.00 w /compacted base & apron 2 Remove / regrade 60 LF 26.85 1,611.00 replace sidewalk Total Revision to Contract Amount $12,151.00 Previous contract amount $ 48,842.45 Net increase in contract amount $ 12,151.00 Revised contract amount $ 60,993.45 Net increase in contract time of completion N/A Revised Contract time of completion N/A The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Date: -7 - 1,1 - q � ec 6edy the City Engineer Agreed to by the Contractor Ap oved by Director of Finance Accepted by t caner Date: 0' (6.9 7 Date: Date: `7 — ) --)