CF-Village-CS 890810 (2) GIi I , INC. CONSULTING EI GII IEER$
August 10, 1989
Mr. Mike Bush
Preload Construction Company, Inc.
839 Stewart Avenue
Garden City, New York 11530
Re: Village Parkway Reservoir
City of Coppe11, Texas
Dear Mr. Bush:
As a point of reference, the contra~t time on the above
referenced project has expired. The required contract completion
date was to be August 9, 1989. As of this date, we have not
received or granted a request for a contract time extension or
substantial completion of this project. Please advise us as to
your intentions and schedules regarding this matter.
Sincerely,
Sanford W. Case, P.E.
cc: Russell Doyle, P.E.
Steve Goram
H. Wayne Ginn, P.E.
Gabe Favre
Randy Fleming
File 381