CF-Village-CS 890712 (2) GINN, INC. CONSULTING ENGINEERS
July 12, 1989
Mr. Frank Trando, Finance Director
City of Coppell
Post Office Box 478
Coppell, Texas 75019
Re:Village Parkway Pump Station
Dual Service Power
Dear Mr. Trando:
Per your June 23, 1989 instructions, we have notified TU Electric
to proceed with providing full dual service power to the Village
Parkway Pump Station as designed. Formal contracts for the City
to execute with TU Electric will be forthcoming. The attached
letter from TU Electric indicates their progress and projected
schedule. Please note the expected delivery date for the
secondary transformer. We will research this matter further to
determine if the Pump Station will be adversely impacted by this
projected date.
Sincerely,
H. Wayne Ginn, P.E. ~..
:.
attachments
Steve Goram
Joe Kotrla, P.E., C.R. McCreary and Associates
Sanford Case, P.E.
File 380
17103 Preston Road · Suite 100 · LB 118 ® Dallas, Texas 75248 · Phone 214/248-4900
l
-- ---- JUL I 2 1989
IIELECTRIC ,
July 10, 1989
Mr. Sanford Case
Ginn Inc.
17103 Preston Road
Suite 100 LB 118
Dallas, Tx. 75248
Dear Mr. Case:
Per our conversation of June 26, 1989 you advised that the City
of Coppell has requested TU Electric to proceed with the 2 feed,
2 transformer service with a customer provided key iffterlock
device for the Village Parkway Pump Station. We are ordering the
second transformer required to provide dual service for this
project. Contracts covering the excess cost of facilities will
be forthcoming.
Please be advised this transformer with 2400/4160 volt three
phase secondary requires a delivery time of approximately 6
months.
Please call me at 323-8910 if you have any questions or concerns
above this project.
Sinc~ely
Tim Brancheau
Sr. Customer Services Representative
TB/rh
cc: P.Y.C.A. Industries, Inc.
P.O. Box 59354
Dallas, Tx. 75229
P. O. Box 819061 Farmers Branch, Texas 75381-906l