Loading...
ST9801-CN000822CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Coppell Road Reconstruction Project # S798 -01 CONTRACTOR: Ed Bell Construction OWNER: City of Coppell CHANGE ORDER NO.: 4 DATE: 8/22/00 Item Description Quantity Unit Unit Price Total Drainage Channel Revisions ADD: 38 CL III RCP 21" 141 LF 43.62 6,150.42 55 12" Grouted Rock RipRap 7 SY 38.00 266.00 Open Back Inlet 1 EA 3000.00 3,000.00 DELETE: Curb Inlet 1 EA 2,000.00 (2,000.00) Total Revision to Contract Amount $7,416.42 Previous contract amount $2,053,542.31 Net increase in contract amount $7,416.42 Revised contract amount $2,060,958.73 Net increase in contract time of completion 40- Revised Contract time of completion _ 292 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Recomme ity Engineer Date �� I"' Agreed to b ontractor ate AccepKd by Owner Date