WA0601-CN090702CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Hunterwood Park Water Line (WA 06 -01) CONTRACTOR: Jim Bowman Construction Company OWNER: City of Coppell CHANGE ORDER NO.: 1 DATE: July 9, 2009 Item Description Quantity Unit Unit Price Total ADD: 1 Concrete Headwall 1 LS $600.00 $600.00 Removal 2 Additional Pavement 18 Sy $50.00 $900.00 Replacement Total Revision to Contract Amount $1,500.00 Previous contract amount $ 42,680.00 Net increase in contract amount $1,500.00 Revised contract amount $44,180.00 Net increase in contract time of completion Revised Contract time of completion The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Recommended y' 'ity Engineer Date p -�- 2.9 Irl gied to b� Contractor Date AccepteO by City