WA0601-CN090702CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Hunterwood Park Water Line (WA 06 -01)
CONTRACTOR: Jim Bowman Construction Company
OWNER: City of Coppell
CHANGE ORDER NO.: 1
DATE: July 9, 2009
Item Description Quantity Unit Unit Price Total
ADD: 1 Concrete Headwall 1 LS $600.00 $600.00
Removal
2 Additional Pavement 18 Sy $50.00 $900.00
Replacement
Total Revision to Contract Amount $1,500.00
Previous contract amount $ 42,680.00
Net increase in contract amount $1,500.00
Revised contract amount $44,180.00
Net increase in contract time of completion
Revised Contract time of completion
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
Recommended y' 'ity Engineer Date
p -�- 2.9 Irl
gied to b� Contractor Date
AccepteO by City