Coppell Ind 2-LR130315 (2)
REPORT OF REINFORCING
STEEL PLACEMENT OBSERVATION
Tradepoint Center II
Creekview Road & Freeport Parkway
Coppell, Texas
REPORTED TO:REPORT NO.
Hillwood 230
3090 Olive Street, Suite 300
REPORT DATE:
03-15-13
Dallas, Texas 75219
REG PROJECT NO.
18520
ATTN: Mr. Kerry Roetzel
DATE OBSERVED:
03-08-13
TECHNICIAN:
J. Bowers
PAGE:
1 of 1
CONTRACTOR:
Hillwood Construction Services
Items Observed: Approach: 85-120’N, 190-270’E from NE building corner.
Pier Caps: C.75/1 and D.5/1.
Slab: Line AA-JJ from 1-2.
Panels: 148-158, 159A and 159B.
Reference Plans or Notes Used: Sheets C-2.01, S-1.00, S-1.01 RFI #32, S-1.1, S-4.00,
S-4.02, Dayton Superior Book and Potter Panel
Elevation book
Comments:Chairs to be installed on slab pour at time of concrete
placement.
X There were no deviations noted.
The reinforcing steel placed at the above referenced locations was observed with
respect to the referenced portions of the contract documents.
E-MailSubmitted by:
Distribution:
(1) Hillwood/Mr. Kerry Roetzel
REED ENGINEERING GROUP, LTD.
(1) Hillwood Construction Services/
Registration Number F-3114
Mr. Gary Jones
(1) Halff Associates/
Mr. Stephen Crawford
(1) Halff Associates/Mr. Lance Clinton
(1) Macgregor Associates/
Ronald F. Reed, P.E.
Mr. Thomas Holland
BW/cdl
(1) Macgregor Associates/
Mr. Lee Rader
(1) City of Coppell/Mr. Lee Stone
(1) City of Coppell/Mr. Michael Arellano
(1) City of Coppell/Mr. Rick O’Dell
(1) Ms. Sacha Miner
2424 STUTZ DR. SUITE 400 DALLAS, TX 75235 [214] 350 5600 [214] 350 0019
TELFAX