Dear Sirs:
A pre-construction conference on the referenced project has been scheduled for
Thursday, April 11, 2013 at 1:30 a.m. in the first floor Conference Room in Town Center
at 255 Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at(972) 304-3684.
Sincerely,
Larry Davis, Construction Inspector
Phone: 972-304-3684
Fax: 972-304-3570
cc: Ken Griffin, P.E., Dir. of Engineering & Public Works
Glenn Hollowell, P.E., Assistant Public Works Director
Michael Garza, P. E., Civil Engineer
Michael Arellano, Chief Building Official
Michael Hodge, Residential Building Inspector
Tim Oates, Deputy Chief/Prevention
David Malone, Deputy Fire Marshal
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
2
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
The owner/ owner's representative will be notified of the date, time and place of
the pre-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner/owner representative's responsibility to notify the following
parties:
• Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
• Geotechnical firm
• Project Engineer
• Contractors or subcontractors for excavation, utility, & paving operations
• SWPPP representative