CF-Andrew Park 1-CS 940113COPPELL PUBLIC WORKS
DATE:
TO:
FROM:
RE:
January 13, 1994
Rick Wieland, Parks & Recreation Manager
R. D. Slayton, Crewleader
Brown Park East Construction Meeting
On Tuesday, January 11, 1994 staff met with Rodman Excavation staff, Steve Giovanninni
from Mesa Design, and Construction Inspector Larry Davis. Several considerations were
brought forth and the following is a list:
1. Wall Relocation. It was determined that the site for the concession was 18"
off-center.
Outfall Estimate. It was brought to staff's attention that the headwall of the
outfall on the north side of Brown Park East is in need of repair.
Construction fence will be installed as soon as details can be worked out
regarding permit.
Pumps to drain the lake will begin operation the week of 17th, weather
permitting. Time of operations will be between 7:00 a.m. and 7:00 p.m.
Larry Davis suggested that the pumps were to use mufflers for noise
abatement.
Rodman will soon remove barricades at the end of Moore. They will install
two (2) twenty foot gates with red and white reflection.
Our next biweekly meeting is scheduled for Tuesday, January 25, 1994 at 9:00 a.m.
RDS/dm