Tax 2010A-CN130514 CITY OF COPPELL • CHANGE OR EXTRA WORK ORDER PROJECT: Tax 2010A Willow Springs Drive CONTRACTOR: RKM Utility Services Inc. OWNER: City of Coppell CHANGE ORDER NO.: 2 DATE: 5/14/2013 Item Description Quantity Unit Unit Price Total ADD: 108 6"Reinforced Pavement with Curb 110 SY $35.50 $3,905.00 111 6"Reinforced 28 SY $37.25 $1,043.00 Driveway/AlleyPavement 112 4"Concrete Sidewalk 287 SY $34.00 $9,758.00 121 10'Curb Inlet 1 EA $2,850.00 $2,850.00 SUBTRACT: Total Revision to Contract Amount $17,556.00 Original contract amount $1,135,632.25 Prior Change Order Amounts $2,500.00 Net increase in contract amount $20,056.00 • Revised contract amount $1,158,188.25 Cumulative increase in TOTAL change order amount(Percentage) 2% Net increase in contract time of completion Revised Contract time of completion 185 The contractor hereby accepts this Contract adjustment as a fmal and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Re X-'9 5 • )4 . /3 m C Date Of— 3 Agree. •ctor Da/e/ Accepted r City /Date