CF-Deforest SC-CS 870713 COPPELL MUNICIPAL SERVICE CENTER
Walk Through Inspection
July 13 1987
'
By: Dick Calvert, Calvert & Co/Architects, Inc.
Randy McCord, MDI, Inc.
Steve Got&m, City of Coppell
Dale Jackson, City of Coppell
Steve Morton, City of Coppell
The following items were noted as being deficient, and requiring
completion and/or correction. While it is intended that this list
is complete, the Owner and/or Architect/Engineer shall retain the
right to amend same as new items may be discovered. The
Contractor shall complete the required correction of all items by
Friday, July 31, 1987.
A. Site:
1. Complete brick screening wall.
2 Install pole light.
3 Install security gate and operator.
4 Install card reader and exit loop at entry gate.
5 Paint entry gate pipe bollards and card reader post yellow.
6 Raise level of fire hydrant to city standard.
7 Install water meter vault and backfill same.
8 Backfill grade along west edge of parking lot. Allow fill
to sift through chain link fence. Southwest corner of
parking lot requires particular attention.
9. Rectify water retaining depression at entry drive over
creek.
10. Repaint parking lot striping where paint was applied over
dirty pavement, particularly at northeast corner of lot.
11. Install landscaping and irrigation system.
12. Final grade all areas to remove evidence of erosion.
13. Take down stock pile of topsoil (% southwest corner of
site) and spread evenly over site.
14. Clean up (by grading) creek channel.
15. R~place broken lid at water check valve.
16. Attach last (chain link) fence posts to building at
northwest and northeast corners of Storage Barn.
17. Complete chain/ink fencing to masonry screening wall.
18. Change "Regular" decal and pump nozzle to "Unleaded"
19. Raise valve stacks near water meter vault.
20. Install metallic sanitary sewer clean-out covers in front
of Storage Barn.
21. Reverse metallic sanitary sewer clean-out covers to east
of Maintenance Building.
B: STORAGE BARN
1. Extend chainlink fabric to roof deck on interior storage
cubicles
.
2. Point-up brick as required.
3. Install vacuum breaker to hose bibb.
4. Grout post-tension cable pockets.
5. Install missing light bulb in center bay.
6. Identify electrical panels, switchgear, and circuit
breakers per specification page 16000-3, paragraph 1.11A
aB.
MAINTENANCE BUIldING "
1. Point-up brick as required.
2. Install fake drain line and escucheon at extra hole in
front wall over electrical switch gear.
3. Install escucheons at all drain-line penetrations.
4. Grout wall penetrations at A/C refrigerant lines.
5. Add handles to mezzanine ladder.
6. Seal concrete floors.
7. WOMEN "F"
a. Correct slow draining lavatories.
b. Convenience outlet at lavatory in not on GFI.
8. MEN "E"
a. Correct slow draining lavatories.
b. Convenience outlet at lavatory in not on GFI.
c. Install missing robe hook at shower.
d. Caulk shower pan to floor.
9. WASH BAY "B"
a. Install lenses on two light fixtures.
b. Install sealant to floor at base of cement fiber
board per SK-5. Note that sea/ant must also seal around
all sides of numerous small pieces of CFB along floor. The
intent of this operation is to render the CFB panel system
generally watertight.
c. Instal/ vinyl base.
d. Correct loose cement fiber board and recaulk/repaint
as required. The intent of this operation is to render the
CFB panel system generally watertight.
e. Install vacuum breaker on hose bibb.
10. BREAKROOM "A"
a. Install wallphone jack.
b. Provide cover for icemaker drain.
c. Install missing screw at strike, Door #
11. OFFICE "M"
a. Instal] silencer on door frame # 20.
12. OFFICE "G"
a. Install fuel management system.
13. Provide A/C test and balance report per specifications.
14. Identify electrical panels, switchgear, and circuit
breakers per specification page 16000-3, paragraph 1.11A
& B.
D: GENERAL
1. Provide "As Built" drawings indicating exact location (by
dimension) and routing of all underground utilities per
specification page 16000-3, paragraph 1.12 A.
2. Provide copies of all warranties, guarantees, operating
instructions, etc. per specification page 16000-4,
paragraph 1.12 B.