Loading...
CF-Deforest SC-CS 861230 December 30, 1986 Mr. Frank Trando City of Coppell P.O. Box 478 Coppell Texas 75019 ' Re: Coppell Municipal Service Center Dear Frank: As you are aware, a major problem has surfaced regarding the subsoil conditions under the paving. When we were originally retained by the city to design the Service Center, we asked for several documents including a current plat of the property and , a soJ. ls investigation of the site. The former City Manager indicated that since the budget was already strained, he did not wish to spend the necessary funds to perform either We were . told to proceed without them. We expressed a concern, but proceeded as we were instructed. Since we didn't have a soils analysis, Pete Hennessey had requested that a city crew take a back-hoe to the site and dig a hole approximately 6' deep so that we might check the soil unde'r the surface. The hole was dug, and Hennessey obtained a bucket full of the soil and delivered it to a testing lab for analysis. The report listed the plasticity index (PI) at 3. We again voiced our concern to the city staff, but were told to proceed. When the plans were complete, we submitted them to the City for review. The various City departments reviewed the plans and issued a building permit on October 27 to proCeed with the construction. On November 17, you, Ed Powell, Steve Goram, and I met in the City Hall Conference Room to discuss several concerns we shared about the project. One of these concerns was the subsoil condition. We discussed the low PI of the soil under the paving. Mr. Powell asked what the paving design was. I stated that generally, the drive has 6" concrete reinforced with #3 bars at 12 inches on center each way, and that the parking areas have 5" concrete reinforced with #3 bars at 16" on center each way. Ed said that he would fee] more comfortable with the stabilization, but since to do so would add approximately approximately $ 60,000 to an already strained budget, that he would approve proceeding with the concrete paving as detailed. At that time, there was no mention made of a City Ordinance requiring stabilization. The construction was begun, and the excavation was completed. During the excavation and filling processes, Haynes & Hollon, the City's Consulting Soils Engineers took numerous soil samples of the various lifts of fill material. The lab tests on some of these samples indicated extremely low to non existent PI readings. When the written reports of these findings reached Steve Morton, your new inspector, he voiced a concern that the subsoils did not meet the requirements of the City Ordinance. Last Nednesday, I was notified by Steve Goram about Mr. Morton's concerns. (This was the first time we had heard of the ordinance.) I called you to discuss the ramifications. We decided to allow the MDI to proceed with their formwork, but not to pour any concrete without authorization. I wrote this instruction to MDI in my letter dated December 24, 1986. I asked MDI to provide us with a price quotation for providing the cement stabilization to the paved areas. Their quotation was for $ 57,600 which I relayed to you by phone on December 29. Mr. Morton had Haynes & Hollon take new soil samples from the areas scheduled to receive paving. These samples were taken yesterday, December 29. The results were to be ready first thing this morning. I called Haynes & Hollon at 9am this morning and was told that some of the samples were still too wet this morning to obtain accurate readings, but that two of the samples yielded PI's of 3.5 and 4.5. I called Mr. Morton, who felt that with these readings, the soil should receive stabilization. I asked him to consult with you, and to Get back to me as soon as possible. Since I hadn't heard back from Mr. Morton by about llam this morning, I went to the jobsite and found the MDI proceeding with their formwork and reinforcing placement. I then proceeded to City Hall to visit with you about the problem. When I arrived, I found that you were out of your office all day. Since we needed direction, I met with Mr. Bowman, and attempted to fill him in on the situation. I explained that as I understood it, we basically had three options. The first was to allow MDI to pour the concrete (in apparent violation of a city ordinance, but in keeping with Mr. Powell's directive); to allow MDI to continue to set formwork and reinforcing (per my letter of December 24) but risking further penalty costs (to the City) of form and reinforcing removal if they later had to be removed to perform the stabilization; or stopping MDI immediately (realizing that MDI would be entitled to additional compensation from the City of some $150 to $200 per day until a determination is made. Mr. Bowman indicated that the next scheduled meeting of the Council is on January 13. He asked that I instruct MDI to stop the work immediately, and to provide a written request to you so that consideration could be given for a special meeting of the Council. I immediately informed MDI of Mr. Bowman's directive. Upon returning to my office, I received a call from Mr. Morton explaining that he was then at the jobsite. He had spoken with George Hollon of Haynes & Hollon who further explained the test results. Of the several samples taken, indeed only two had been dry enough to complete the testing. Of those two, the lowest PI was 3.? and the other was 4.5. Mr. Hollon examined the remaining samples and estimated that none were more sandy than the 3.? sample, thus their PI should be above 4. These test results should be available early tomorrow mor.n~ng. Based upon the assumption that the readings would be Greater than 4, Mr. Morton authorized MDI to schedule the pour for lOam tomorrow. He explained to me that while the ordinance requires stabilization of soils with PI's below 6, that his discretionary powers allow him to vary as much as 2 points either way, and that since readings above 4 would be within this range, he was allowing the Contractor to proceed. I hope that you realize that this letter is in no way intended to be critical of any individual, but only to serve as documentation of a very confusing sequence of events. The fact that we did not have a soils analysis from the beginning Greatly compounded the problem. We were the architects on the new facility for Shake & Shingle Supply at 200 E. Belt Line Rd. This facility was completed during May of 1986. Their paving subgrade was not stabilized. We purchased a Coppell Subdivision Ordinance prior to designinG Shake & Shingle. We can find no reference to this requirement in our copy. On the assumption that the ordinance was adopted subsequent to the printing of our copy, why wasn't the problem addressed during the review of our plans and specifications for the building permit? While admittedly Mr. Morton has information available to him now that was not available to Mr. Powell, why wasn't the issue City Ordinance addressed earlier? AGain, hopefully we can al/ learn from this experience. The lack of adequate information up front and the timing of the red flag could have cost all of us. Richard A. Calvert, AIA cc: Steve Goram ~eve Morton Vivyon Bowman Frank Pieschel Pete Hennessey