Tax 2011B-CN130228CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Vanbebber Drive - Tax 2011B
CONTRACTOR: CPS Civil, LLC
OWNER: City of Coppell
CHANGE ORDER NO.: Three (3) DATE: February 28, 2013
1. This change order rectifies final quantities with as -built field conditions, and increases the value of the
contract to cover the additional work performed.
Item
Description
Quantity
Unit
Unit Price
Total
ADD: 104
Remove & Dispose Ex.
47
SY
$8.00
$376.00
Concrete Pavement
Remove & Dispose Ex.
105
Concrete Driveways, Alleys
177
SY
$8.00
$1,416.00
& Sidewalks
109
8" Reinforced Pavement
72
SY
$35.00
$2,520.00
with Curb
8" Stamped Concrete
110
Pavement with Integral
7.56
SY
$60.00
$453.60
Color
111
6" Reinforced
142
SY
$37.00
$5,254.00
Driveway /Alley Pavement
112
4" Concrete Sidewalk
57
SY
$30.00
$1,710.00
114
Variable Height Ret. Wall
42
LF
$40.00
$1,680.00
w /Integral Sidewalk
121
10' Curb Inlet
0.50
EA
$3,000.00
$1,500.00
124
18" Reinforced Concrete
I
LF
$50.00
$50.00
Pipe (CL III)
128
8" PVC C -900 DR -14
37
LF
$50.00
$1,850.00
Water Line
Total Additions
Delete: 146
$16,809.60
Trench Safety for All (88) LF $1.00 ($88.00)
Utilities
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
Total Deletions
($88.00)
Total Revision to Contract Amount: $16,721.60
Original contract amount $588,100.00
Net increase in contract amount $16,721.60
Previously approved changes $21,086.00
Revised contract amount $625,907.60
Cumulative increase in TOTAL change order amount (Percentage) 6.4%
Net increase in contract time of completion 14
Revised Contract time of completion 136 Calendar Da s
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord
Agreed to
zo� --/- 7,��- J�
Accepted City Da e