Loading...
CF-Village-CS 890201 (2) GINN, INC. CONSULTING ENGINEERS February 1, 1989 Mr. Russell Doyle, P.E., City Engineer Ii Post Office Box 478 Coppell, Texas 75019 Re: Village Parkway Pump Station Change Order #1 Dear Mr. Doyle: As you are aware, the condition of Kimbal Kourt has deteriorated due in part to the increased traffic related to construction of the 4.0 MG ground storage tank. With the pump station just beginning construction, the road condition is expected to further worsen. To correct this condition, Cajun Contractors, Inc. has approached us with the following proposal: 1) Replace the proposed 48" bored crossings along Sandy Lake Road at Station 24+10, 27+01, and 30+55 with open cut crossings. These crossings are at entrances to the Corners of Coppell shopping center. 2) Replace the proposed 24" bored crossings along Kimbal Kourt at Station 32+74 and 33+72 with open cut crossings. These crossings are at entrances to the Stop-N-Go strip center. 3) Replace the proposed 24" bored crossing of Kimbal Kourt at Station 36+90 with an open cut crossing. All open cut crossings will be subject to the following conditions: 1) No more than one (1) entrance to the Corners of Coppell shopping center will be closed at any time. 2) No more than one (1) entrance to the Stop-N-Go strip center will be closed at any time. 3) All concrete drives will be saw cut or removed at expansion joints and replaced per original condition. 4) All open cut operations will be performed in the public right-of-way. 17103 Preston Road · Suite 100 · LB 118 · Dallas. Texas 75248 · Phone 214/248-4900 In exchange for allowing the above open cut crossings, the contractor is offering the following: 1) Adjust the proposed 36" water main at station 10+87 to avoid utility conflicts. 2) Adjust the proposed 36" water main at Sandy Lake Road to avoid utility conflicts. 3) Prior to completion of the Village Parkway Pump Station project, Cajun Contractors, Inc. will pulverize, recompact, and install a 2" H.M.A.C. surface to Kimbal Kourt from Sandy Lake Road to Village Parkway. We wish to note that this work will require Kimbal Kourt to be closed during the boring of Sandy Lake Road, the open cutting at Station 36+90, and for resurfacing. The only facility which will be briefly denied access during this process is the old Police Station on Kimbal Kourt. The contractor has proposed this Change Order at no change to the contract amount. We believe it is in the City's best interest to accept this change order. If you concur, please forward this Change Order to Mr. Ratliff for his approval. If we can be of further assistance or if you have any questions, please contact us. Sincerely, San~ford W. Case, P.E. attachment cc: Steve Goram Karl Hirschey, Cajun Contractors, Inc. H. Wayne Ginn, P.E. File 380