RE: Project#DR 12-01, Creekview Dr. Retaining Wall&Roadway Improvements
NOTICE TO PROCEED WITH CONSTRUCTION
Dear Mr. Frazier:
This letter will serve as your official notice to begin work on the referenced project on June
20, 2013. One hundred fifty (150) Calendar Days were bid on this project for the
completion of work. Therefore, if work begins on June 20th, then the calendar days on the
project will expire on November 17, 2013. Your construction time will officially begin the
day of commencement or June 20th,whichever is first.
If you have any questions or need any additional information, please feel free to contact
Larry Davis, Construction Inspector, at(972) 304-3684.
Sincerely,
i
George M. shall, P.E.
Civil Engineer
Office 972-304-3562
Fax 972-304-3570
gmarshall@coppelltx.gov
cc: Kenneth M. Griffin, P.E.,Director of Engineering&Public Works
Larry Davis, Construction Inspector
Glenn Hollowell, P.E.,Assistant Director of Public Works
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673