From:Jennifer Clardy <jen@prestoncontractors.com>
Sent:Monday, July 01, 2013 1:55 PM
To:Rhonda Adloo
Subject:RE: 724 Canyon Drive.
Importance:High
Yes, one is being overnighted to me and the other is being worked on.
From: Rhonda Adloo [mailto:RAdloo@coppelltx.gov]
Sent: Monday, July 01, 2013 1:49 PM
To: Jennifer Clardy
Subject: RE: 724 Canyon Drive.
Have you checked with your subs about their maintenance bonds? I know we must receive those prior to Engineering
issuing a final acceptance letter, but that may not have much to do with a temporary CO.
From: Jennifer Clardy [mailto:jen@prestoncontractors.com]
Sent: Monday, July 01, 2013 12:33 PM
To: Rhonda Adloo
Cc: Tim McMahon; Jennifer Clardy
Subject: RE: 724 Canyon Drive.
Importance: High
Ok, so does Spairs still need to submit a final set? Also, any word on the streets punch list?
From: Rhonda Adloo [mailto:RAdloo@coppelltx.gov]
Sent: Monday, July 01, 2013 12:31 PM
To: Jennifer Clardy
Subject: RE: 724 Canyon Drive.
I just found out the as-builts are OK. Building Inspections Dept. does the temporary CO’s
From: Jennifer Clardy [mailto:jen@prestoncontractors.com]
Sent: Monday, July 01, 2013 12:06 PM
To: Rhonda Adloo
Cc: Tim McMahon; Jennifer Clardy
Subject: RE: 724 Canyon Drive.
Importance: High
Rhonda,
I was wondering, could we get a Temp CO without these items?
From: Rhonda Adloo [mailto:RAdloo@coppelltx.gov]
Sent: Monday, July 01, 2013 10:17 AM
To: Jennifer Clardy
Subject: RE: 724 Canyon Drive.
1
Since we only received the as-builts late on Thursday afternoon, I can safely say they probably have not been looked
at yet.
rd
I don’t know what a 3 party energy inspection is, but I imagine it goes to the Building Inspections Dept.
The Streets Dept. punch list is on its way to me right now, will let you know ASAP if anything is left on it.
From: Jennifer Clardy [mailto:jen@prestoncontractors.com]
Sent: Monday, July 01, 2013 8:34 AM
To: Rhonda Adloo
Cc: Tim McMahon; Jennifer Clardy
Subject: 724 Canyon Drive.
Importance: High
Good morning Rhonda, hope you had a good weekend. I was following up on the status of the Streets Dept.
punchlist. Also, I was wondering if I could get a status on the review of the prelim as builds.
rd
On the 3 party energy inspection, who do I send that to? I have it completed.
PLEASE NOTE OUR NEW ADDRESS…
Jennifer Clardy
Operations Manager
Preston General Contractors, LLC
13740 Midway Road, Suite 603
Dallas, Texas 75244
972.890.7373 Cell
972.991.0498 Office
972.991.0499 Fax
2