MA FY 12/13-CN130624 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Annual street and alley contract CONTRACTOR: Laughley Bridge& Construction,Inc. OWNER: City of Coppell CHANGE ORDER NO.: One(1) DATE: June 24,2013 1. This change order is to pay for the extra flex base needed to repair a pavement section. Item Description Quantity Unit Unit Price Total ADD: 1 excavate soil and replace 308.5 ton $30.00 • with flexbase $9,255.00 Total Additions $9,255.00 Total Deletions $0.00 Total Revision to Contract Amount: $9,255.00 Original contract amount $450,000.00 Net increase in contract amount $9,255.00 Previously approved changes $0.00 Revised contract amount $459,255.00 Cumulative increase in TOTAL change order amount(Percentage) 2.1% Net increase in contract time of completion 0 Revised Contract time of completion 0 Calendar Days CITY OF COPPELL CHANGE OR EXTRA WORK ORDER The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord JA Recom ended by ity ngineer Date VP 3 Agrees to by Co 'ctor / Date / Accepted b qty Date